Hello,Currently in projectmgr, the actualCompletionDate of task, phase and project are calculated by :
1) max(actualCompletionDate) for task or all task in phase or in project2) if there are some timeEntries and if max(thruDate) of all timeEntries > max(actualCompletionDate), use "max(thruDate) of all timeEntries"
I think that point 2 is wrong, only 1) should be used. If everybody is OK, i will submit the patch Olivier Heintz