A couple of additions:

1. Include the time estimates for the sub-tasks as well. For example:

    - [ ] Create draft       ( 2h)
    - [ ] Insert screenshots (15m)
    - [ ] Review post        (30m)
    - [ ] Publish document   (15m)

  The total time estimate for the task should be the sum of the time estimates 
for the individual sub-tasks.

2. For each sprint, include a work per day (wpd) estimate in the PROPERTY as 
shown below:

    ** October   10, 2018 - October  23, 2018 (14 days)
       :PROPERTIES:
       :wpd-mbuf: 2
       :END:

SK
--
Shakthi Kannan
http://www.shakthimaan.com