Bob,
I've got this from the
VERITAS Netbackup 6.0 Administration course manual :
"Frequency
Select the frequency radio
button to enable administrators to specify how much time must elapse between the
successful completion of a scheduled task and the next attempt at the
task"
Cheers,
Tim From: [EMAIL PROTECTED] [mailto:[EMAIL PROTECTED] On Behalf Of Bob Stump Sent: Thursday, 18 May 2006 10:28 PM To: Wilkinson, Tim; veritas-bu@mailman.eng.auburn.edu; Tristan Ball Subject: RE: [Veritas-bu] 'Frequency' schedule type "frequency is measured from when the backup
ends"
Will someone please provide me the
documentation that states this?
I have been looking for it for literally
YEARS...
>>> "Tristan Ball" <[EMAIL PROTECTED]> 5/17/2006 10:07 PM >>> Yes - and be aware that the frequency is measured from when the
backup ends!
I use 5 days on my "weekly" backups, and 12 hours on my nightly's.
:-)
t.
---
Tristan Ball
System Administrator
Vision Systems
+61-3-9211-7064
From: [EMAIL PROTECTED] [mailto:[EMAIL PROTECTED] On Behalf Of Wilkinson, Tim Sent: Thursday, 18 May 2006 10:48 AM To: veritas-bu@mailman.eng.auburn.edu Subject: [Veritas-bu] 'Frequency' schedule type Hi,
I'm trying to understand
how this actually works as I think it works a little differently from how I
thought it worked. We have a couple of polices that do a full backup weekly,
with the frequency set to 1 week. However, the jobs didn't run on the weekend;
there were no errors, they just didn't run.
The only reason I can think
of this happening is the job falling outside of the start window. From what I've
read, the frequency is the minimum amount of tim that must pass before the next
schedule runs, which means that we should probably set the weekly jobs to having
a frequency of 6 days to avoid it falling outside the start window. Would this
be correct?
Cheers,
---------------------------------------------------------------------
Tel: (02) 96921484 |
- RE: [Veritas-bu] 'Frequency' schedule type Wilkinson, Tim
- RE: [Veritas-bu] 'Frequency' schedule type Tristan Ball
- RE: [Veritas-bu] 'Frequency' schedule type Bob Stump
- Re: [Veritas-bu] 'Frequency' schedule type Eric Ljungblad
- Re: [Veritas-bu] 'Frequency' schedule type bob944
- Re: [Veritas-bu] 'Frequency' schedule type Mansell, Richard