Notes

Attendees:

Shane, Dave, Saul, Darren, Richard, Tom, Julie, Ke, ScottG, JeffO, Paul, 
Jessica, Bruce, Beth, Dennis (TI)

Agenda:
*       Review Yocto 1.1 M1 Release Criteria - 10 min (Julie)
*       See details at: 
https://wiki.yoctoproject.org/wiki/Yocto_Project_v1.1_Release_Criteria
*       Everything is green. We achieved this in the sense that the team has 
reached a conscious decision to move something from M1 to M2. Next time, we 
should have some must-have features defined before we go into next milestone.
*       Yocto and BSPs were build.
*       New bugs: 1037 is for M1, but this is not a show stopper. We are ok 
with this.
*       No high bugs

*       Discuss M1 1.1 M1 Release Status, go/no-go vote - 10 min (Julie)
*       Beagle board can be built now, is under testing
*       Our goal of these milestones is to have some major features 
accomplished.
*       We have a conditional go for M1 provided that we get test result for 
beagle board test result, and no show stoppers.
*       Proposed plan:
1.      Saul: Check test result with Jiajun and see if there is any show 
stoppers
2.      Beth send email for release
3.      Dave follow up with a blog entry
*       Review progress on M2 P1 items (see below) with incomplete designs - 30 
min (Song)
*       N+1 testing for distro testing is on for next milestone. N+1 is the 
current production version plus the next Alpha version
*       LayerTooling design review: AR: Richard to review these items
*       Image creator: Jessica sent the detailed task list. Jessica signed off 
the design for these items. The team feels comfortable with the schedule. AR: 
Song to update the wiki.
*       Multi-lib: we will have separate meeting to address this.
*       Bug assigning process for bugs assigned to BSP/Tom:
*       Bugs assigned to BSP/Tom are not necessarily BSP related. Tom would 
like to be involved in the bug triage process.
*       Don't want to put a barrier for people to file bugs by asking people to 
spend more time on where the bug should belong when they file bugs.
*       QA team is very resource limited, probably not appropriate to ask them 
to spend more time analyzing bugs.
*       Solution: AR: Darren will check new BSP related bugs more regularly and 
work with Tom to reassign them if needed.
*       Opens:
*       PPC bugs (414): short term we cannot do much. Mark talked to people in 
PPC community.   WRS team has some plan and directions to go. Work is still in 
progress. We need help on resources. Find someone to work on it in July-Sep. 
period maybe. AR: Dave to bring this up to the advisory board for help.
*       Bruce is good with the current feature and schedule including p2/p3 
items.


             Updates marked in yellow
Feature Name    Description     Priority        Commit  Status  Owner   Design 
Signoff  Due     Comments / Bugzilla Links
Error handling in bitbake (Design)      Performance improvement (gather input 
from community on use cases)      1       Yes     Accept  Saul (Scott G)   
Richard        M2,Sprint B     M2, Sprint A, (Scott to talk with Richard about 
the design of this item and then come back with update)
Filed bugs (enhancement) in bugzilla, working on priorities and figure out what 
need to be done in the next 2 weeks.
multi-lib complete      multi-lib support for 32-bit & 64-bit and capable of 
being installed at the same time fully complete    1       Yes     Accept  
Richard (Qing/Ke)               M2, Sprint D    M2, Sprint D
Image Creator polish    polish and refine Image Creator - See 
https://wiki.yoctoproject.org/wiki/BitBake/GUI/PostOneOh for details      1     
          Accept  Josh            M2, Sprint D    M2, Sprint D, Jessica/Josh 
will work on these items
kernel bloat - development      target = boot a minimal image in < 8M - 
development complete    1               Accept  Darren          M2, Sprint D    
M2, Sprint D
LayerTooling - Dependency handling      Dependency handling     1               
M2, Sprint C    Paul            M2, Sprint C    M2 Sprint C, dependent on 
Sprint C item (LayerTooling), check next Tuesday
LayerTooling - layer merging tool       Tool to merge (flatten) several layers 
into one 1               M2, Sprint C    Paul            M2, Sprint C    M2, 
Sprint C, under review (Richard)
LayerTooling - remote layer tool        Consider integrating Jeremy Puhlman's 
remote layers patch       1               M2, Sprint C    Ke/Paul         M2, 
Sprint C    Jeremy is working on this, M2, Sprint C
Package config option enhancement - Plan        Plan our approach to package 
config option enhancement  2               M2, Design      Richard              
   M2, Design
multi-lib infrastructure        multi-lib support for 32-bit & 64-bit and 
capable of being installed at the same time - infrastructure in place (multilib 
toolchain changes, configuration changes)     1       Yes     M2, Sprint A    
Richard(Qing/Ke)                M2, Sprint B    M2, Sprint A, Sprint B
multi-lib RPM   RPM support for multilib added  1               M2, Sprint B    
Richard (Qing)          M2, Sprint B    M2, Sprint B, too large, dependent on 
other features, Mark owns the architecture, leave for discussion with PRC team
LayerTooling - output info enhancement  1) Show a parse error if a bbappend 
matches no existing bb. 2) Update banner info to show layers being used and 
revisions/branches for each one if available    1       Yes     M2, Sprint B    
Dexuan          M2, Sprint B    M2, Sprint B, Richard will look at the design 
again for these(LayerTooling), need discussion with PRC team
Layer Tooling - Architecture    Implement Layer Tooling changes 1       Yes     
Accept  Richard (Paul/Daoxien will help)        n/a     M2, Sprint A    M2 
Sprint A, still dependent on Jeremy
Optimize support for Intel hardware features    We need to understand and track 
each important Intel hardware feature and how it should be optimally supported 
in the Intel BSPS. Items that immediately come to mind are power, video, and 
performance counter settings, etc.  1               on-going        Tom/Darren  
            M2, Sprint A    M2, Sprint A, Tom/Darren will work together on the 
design (possibly break up this item), target: ww24.1

We had a kernel meeting, we have a list of items (a handful of) and will enter 
them in bugzilla. Will plan these bugs at milestone level instead of at Sprint 
level

Remove this from feature list, track them in bugzilla
kernel bloat - analysis (Design)        target = boot a minimal image in < 8M - 
analysis complete       1       Yes     Accept  Darren          M2, Sprint B    
M2, Sprint B, need to have specifics and design

Beagle board kernel fix is taking longer than expected, this one needs to be 
moved to Sprint B.
LayerTooling - combo layer tool Tool to manage combination repos (e.g. the poky 
repo)   1       Yes     70%     Ke              M2, Sprint A    M2, Sprint A
Changes for Image Creator - phase 3     Phase 3: package format job done + 
image output type job done   1               Accept  Joshua                  
M2, Sprint B, needs to work Joshua and rearrange
Changes for Image Creator - phase 4     Phase 4: complete plug-in       1       
        Accept  Jessica                 M2, Sprint D, need reschedule