Thanks you all for your support the team's hard work on the 1.2 release. We 
made it! 


Attendees:
Beth, Nitin, Richard, Jefro, Tom, Darren, Saul, Mark (MontaVista), Jeremy 
(MontaVista), Mark, Jessica, Denys (TI), ScottR, Song
 
Agenda:
 
* Release Criteria review, 
 
- Functional Completion: Completed all bug 2 P1 features. The 2 P1's are mostly 
completed and pushed to 1.3 to finish up, they are not release blockers at this 
point. We also completed most of the P2's and P3's. Overall the team has 
completed more than 75% of what we planned as a 'goal' for our 1.2 release.
 
- Build & release (Yocto Project and core BSPs): all features and core BSPs can 
be built with no error.
 
- Open Bugs: all high bugs are fixed, team fixed all 1.2 must fix bugs. 
 
- Functional Test: Full pass test has been run on RC2, all completed, bugs are 
logged.
 
- Distro Tested: N+1 for Fedora, OpenSuse, Ubuntu, Centos. World image testing 
has not been completed due to Shanghai QA team's holiday schedule and power 
issue. But the QA team feels that we should not have any significant issue 
there. And we have tested this in RC4.
 
- Core BSP: all core BSPs are tested and bugs are logged.
 
- Documentation: minor changes not in the release tarball, will be pulled into 
1.2 release branch.  5 or 6 changes affect the correctness of the doc. Please 
check out the latest doc from the 1.2 release branch.
 
- Build Performance: 111 min for RC5, at pretty much the same level as we 
started the release (104 min) considering deviations.
 
- Package Update/Upstream statues: Target met
 
* Vote:
- The team including all communities members on the call approved the 1.2 
release and we are going to release today on April 30th, 2012.
 

-----Original Appointment-----
From: Liu, Song 
Sent: Friday, April 27, 2012 1:53 PM
To: 'Anders Darander'; Barros Pena, Belen; Bodke, Kishore K; 'Bruce Ashfield'; 
'Daniel Cauchy'; 'deVries, Alex'; 'Dixon, Brad'; Dmytriyenko, Denys; Erway, 
Tracey M; Flanagan, Elizabeth; Hart, Darren; 'Hatle, Mark'; 'Jeremy Puhlman'; 
Kooi, Koen; Kridner, Jason; Li, Susie; 'lieu...@windriver.com'; Lock, Joshua; 
'McCombe, Kevin'; Moeller, Thorsten; 'mor...@mvista.com'; Osier-mixon, Jeffrey; 
'Polk, Jeffrey'; Purdie, Richard; 'Ranslam, Rob'; Saxena, Rahul; Stewart, David 
C; Wang, Shane; Wold, Saul; Yu, Ke; Zanussi, Tom; Zhang, Jessica; 
yocto@yoctoproject.org; Mueller, Robert; Arce Moreno, Abraham; 'Ravi Vompolu'; 
Rifenbark, Scott M; 'Hudson, Sean'; 'Mitchell, Jeffrey - 0665 - MITLL'
Cc: mor...@mvista.com; Darren Hart
Subject: Yocto Project 1.2 release readiness meeting
When: Monday, April 30, 2012 8:00 AM-9:00 AM (UTC-08:00) Pacific Time (US & 
Canada).
Where: Bridge Info Enclosed


Monday, April 30, 2012, 08:00 AM US Pacific Time 
916-356-2663, 8-356-2663, Bridge: 1, Passcode: 4364030
Speed dialer: inteldialer://1,4364030 | Learn more


_______________________________________________
yocto mailing list
yocto@yoctoproject.org
https://lists.yoctoproject.org/listinfo/yocto

Reply via email to