On 01/22/2016 08:29 AM, Jolley, Stephen K wrote:
> Current Dev Position: YP 2.1 M2
> Next Deadline: YP 2.1 M2 Cutoff (Feature Freeze) date is January 25, 2016 
> noon GMT
> 
> SWAT team rotation: Randy -> Benjamin
> https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team
> 
> Key Status/Updates:
> 
>   *   Yocto Project 2.0.1 was successfully built and is due out of QA soon, 
> likely to release next week.
>   *   Yocto Project 2.1 M2 cutoff is on Monday, please ensure any patches 
> expected to be in M2 are sent to the mailing list for review before then.
>   *   We are looking pretty up to date with patch review/processing although 
> there is a large queue in -next pending final checks but which should merge 
> soon.
>   *   We are keeping an eye on CVEs and ensuring they get merged to various 
> branches as we can find the bandwidth but we're low on manpower for this.

What CVEs need merging? New ones or ones submitted for stable branches?

- armin


>   *   I'd like to highlight that there are increasing numbers of stack 
> overflow questions about the project and help in providing good answers on 
> there would be appreciated.
>   *   WDD and bug trend continue to rise to new heights. We are simply 
> receiving more bugs than we have resources to fix/close.
> 
> Key YP 2.1 Dates:
> YP 2.1 M2 Cutoff (Feature Freeze) date is January 25, 2016 noon GMT
> YP 2.1 M2 Target release date is February 12, 2016
> YP 2.1 M3 Cutoff (Feature Freeze) date is February 29, 2016 noon GMT
> YP 2.1 M3 Target release date is March 18, 2016
> YP 2.1 M4 / Final Cutoff: March 28, 2016 noon GMT - Stabilization only 
> milestone.
> YP 2.1 Final Release Target: April 29, 2016
> 
> Key Status Links for YP:
> https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.1_Status
> https://wiki.yoctoproject.org/wiki/Yocto_2.1_Schedule
> https://wiki.yoctoproject.org/wiki/Yocto_2.1_Features
> 
> Tracking Metrics:
>             WDD 2581 (last week 2524 )
> (https://wiki.yoctoproject.org/charts/combo.html)
> 
> [If anyone has suggestions for other information you'd like to see on this 
> weekly status update, let us know!]
> 
> Thanks,
> 
> Stephen K. Jolley
> Yocto Project Program Manager
> INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
> *   Work Telephone:          (503) 712-0534
> *    Cell:                                (208) 244-4460
> * Email:                             stephen.k.jol...@intel.com
> 
> 
> 
> 
-- 
_______________________________________________
yocto mailing list
yocto@yoctoproject.org
https://lists.yoctoproject.org/listinfo/yocto

Reply via email to