Current Dev Position: YP 2.2 M1

Next Deadline: YP 2.2 cut off: June 13, 2016


SWAT team rotation: Tracy -> Alejandro

https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team


Key Status/Updates:

*        Python3 is nearly ready to merge, 4 oe-selftest issues remain and some 
toaster issues. There are likely others but the tests aren't showing them and 
I'm not getting bug reports so the code will merge once the known issues are 
addressed.

*        gcc6 is about ready to merge, just one issue, linux-yocto-4.1 on 
beaglebone to address

*        Patches are being held up as some large series (python3, gcc6) are 
needing testing and we're trying to get these done before moving to other 
patches. We're aware there is a backlog building again and will work through 
that as time and autobuilder resources allow.

*        RP is out of contact Fri-Mon due to vacation/national holidays so this 
may delay some final merges, mut is continuing development. RP typically does a 
lot of testing over weekends to make the most of the autobuilder but this won't 
happen and hence there will be a slow down.

*        YP 1.8.2 passed QA and is due for release shortly.

*        YP 2.0.2 is in QA and will be out next week.


Key YP 2.2 Dates:

*        YP 2.2 M1 cut off would be: 6/13/16

*        YP 2.2 M1 release would be: 6/24/16

*        YP 2.2 M2 cut off would be: 7/18/16

*        YP 2.2 M2 release would be: 7/29/16

*        YP 2.2 M3 cut off would be: 8/29/16

*        YP 2.2 M3 release would be: 9/9/16

*        YP 2.2 M4 cut off would be: 10/3/16

*        YP 2.2 M4 release would be: 10/28/16


Tracking Metrics:

            WDD 2574 (last week 2626)

(https://wiki.yoctoproject.org/charts/combo.html)


Key Status Links for YP:

https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.2_Status

https://wiki.yoctoproject.org/wiki/Yocto_2.2_Schedule

https://wiki.yoctoproject.org/wiki/Yocto_2.2_Features

[If anyone has suggestions for other information you'd like to see on this 
weekly status update, let us know!]

Thanks,

Stephen K. Jolley
Yocto Project Program Manager
INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
*   Work Telephone:        (503) 712-0534
*    Cell:               (208) 244-4460
* Email:                            stephen.k.jol...@intel.com
-- 
_______________________________________________
yocto mailing list
yocto@yoctoproject.org
https://lists.yoctoproject.org/listinfo/yocto

Reply via email to