Current Dev Position: YP 2.4 M4

Next Deadline: YP 2.4 Final Cut off is Sept. 18, 2017


SWAT team rotation: Alejandro -> Stephano on Sept. 15, 2017.

SWAT team rotation: Stephano -> Maxin on Sept. 22, 2017

https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team


Key Status/Updates:

·        YP 2.3.2 (pyro) is in progress and in QA about 57% complete.  See: 
https://wiki.yoctoproject.org/wiki/2.3_QA_Status

·        YP 2.2.2 (morty) has been through QA but there were a number of issues 
raised. See: 
https://wiki.yoctoproject.org/wiki/WW37_-_2017-09-13_-_Full_Point_Release_Test_Cycle_2.2.2_rc2

·        For 2.2.2, we are currently working on understanding the impact of one 
remaining issue in order to decide if it can be released, the issue concerns 
the presence of ptest packages in test images. There were a number of other 
issues raised or open, many of the open issues were resolved in 2.2.2 and have 
been closed, some other issues were due to confusion of testing morty compared 
with master (which has a different eSDK configuration).

·        The rocko branches for 2.4 and the bitbake 1.36 branches have been 
created in preparation for the 2.4 release rc builds which are due soon.

·        The branch name for the ‘2.5’ release is “sumo” 
(https://wiki.yoctoproject.org/wiki/Releases has been updated).

·        For 2.4 we continue to have a number of concerning issues, 
particularly in pseudo but on other areas too. Patches are being worked upon, 
the patch backlog should be mostly under control at this point. Technically we 
are due the first 2.4 rc build today, reality is we need to fix several more 
issues before we do that. We have had some image size issues we’re struggling 
to pin down to a specific patch and that is holding up a number of patches 
whilst we bisect where the issues are.


Planned upcoming dot releases:

YP 2.2.2 Cut off June 5, 2017 - Pending release soon.

YP 2.2.2 Release by June, 16 2017

YP 2.3.2 Cut off Sept. 1, 2017 - In QA now.

YP 2.3.2 Release by Sept. 15, 2017


Key YP 2.4 Dates are:

YP 2.4 M4 (Final) Cut off is Sept. 18, 2017

YP 2.4 M4 (Final) Release by Oct. 20, 2017


Tracking Metrics:

            WDD 2456 (last week 2540)

(https://wiki.yoctoproject.org/charts/combo.html)


Key Status Links for YP:

https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.4_Status

https://wiki.yoctoproject.org/wiki/Yocto_2.4_Schedule

https://wiki.yoctoproject.org/wiki/Yocto_2.4_Features


[If anyone has suggestions for other information you’d like to see on this 
weekly status update, let us know!]


Thanks,

Stephen K. Jolley
Yocto Project Program Manager
INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
•   Work Telephone:        (503) 712-0534
•    Cell:               (208) 244-4460
• Email:                          stephen.k.jol...@intel.com

-- 
_______________________________________________
yocto mailing list
yocto@yoctoproject.org
https://lists.yoctoproject.org/listinfo/yocto

Reply via email to