I don't know the official answer.
But the ones I have seen, the client has started a backup, but never
finished, and never reported the correct status back to the server.
Check the client dsmsched.log to be sure.

-----Original Message-----
From: Hussein Hasan [mailto:[EMAIL PROTECTED]
Sent: Tuesday, July 29, 2003 5:02 AM
To: [EMAIL PROTECTED]
Subject: scheduled events status report






Hi  fellows

 Some time,  when I  request  the status report of the scheduled events ,
one or more clients  showing
  status value  = (?)  ,
 what does it mean  and why   ?
here is an example :-

Scheduled Start      Actual Start         Schedule Name Node Name
Status
-------------------- -------------------- ------------- -------------
---------
28-07-2003 19:10:00  28-07-2003 20:54:08  STOS1         STO_CR_AMNH
Completed
28-07-2003 19:10:00  28-07-2003 20:37:02  WEBS1         WEB_IT_CPLX
Completed
28-07-2003 19:10:01  29-07-2003 01:18:45  PERS1         PER_HQ_CNTR   (?)

28-07-2003 19:10:08  28-07-2003 23:14:01  SIGS1         SIG_IT_CPLX
Completed
28-07-2003 19:10:31  28-07-2003 21:48:06  ARCHQS1       ARC_HQ_CNTR
Completed

Thanks alot in advance

This e-mail Message is Intended for the named Recipient Only. It May be
Privileged and/or Confidential. If you are NOT the Intended Recipient of
this e-mail then you Should NOT Copy it or Use it for any Purpose, Nor
Disclose its Contents to any Person. You Should Contact The Housing Bank
For Trade and Finance as Shown above So that we can Take Appropriate Action

Reply via email to