Paying “per foot” for directional drilling….
Is like comparing “per pound’ on what it costs to buy a car. Cobalt or
Cadillac…
Soil conditions, permits, product, travel time, etc… all make the difference.
If there was 1150ft drilling work across the street from me… I would do it for
$4000.
If it was any of –
2 hour drive
Stones and cobble
Need excavator to dig start/end holes
Separate reel trailer
Special mud mixing
Entering a building under the grade beam
Close to the surface of asphalt (risk to break it up / damage it)
The price could hit $10 and even $25-30/foot
When someone has the equipment to make it look easy…. That equipment might be
worth a million bucks.
From: Af [mailto:[email protected]] On Behalf Of Chuck McCown
Sent: Tuesday, May 9, 2017 10:03 AM
To: [email protected]
Subject: Re: [AFMUG] Directional Boring Quote / Costs
I used to get that price, but now-a-days all the boring companies are sooo busy
and booked up they have all increased their pricing.
From: Kurt Fankhauser
Sent: Tuesday, May 09, 2017 8:35 AM
To: [email protected] <mailto:[email protected]>
Subject: Re: [AFMUG] Directional Boring Quote / Costs
that pricing sounds right
On Tue, May 9, 2017 at 8:50 AM, Paul McCall <[email protected]
<mailto:[email protected]> > wrote:
On my project, I am doing some DBs and have a quote that I want to compare to
see if its inline. It probably is, I am just dealing with sticker shock of $
15K to do this.
It is actually 4 bores (has to make some right angles without room for
“sweeps”, totaling 1150 feet at $13 per foot, including 3” HDPE pipe laid in
soft ground 36” deep.
Paul
Paul McCall, President
PDMNet, Inc. / Florida Broadband, Inc.
658 Old Dixie Highway
Vero Beach, FL 32962
772-564-6800 <tel:(772)%20564-6800>
[email protected] <mailto:[email protected]>
www.pdmnet.com <http://www.pdmnet.com>
www.floridabroadband.com <http://www.floridabroadband.com>