Hi Barbara,

 

A little long winded but here we go.

 

I had a customer that used the Change Request part of the Help Desk for such
a process. The Production Change Request (PCR) was the most important so
that is where we started. We created a process that would automatically
create tasks for the groups/people that needed to approve or perform a
technical review before a change could be moved to production. We created a
custom form to house the task matrix that was based on a 3 letter system
code that was set on the CR when the CTI was set.

 

The next phase was to bring the developer teams onboard to track their work.
They would create Change Requests in their own special view for their
development projects and had automatic tasks that support their Software
Development Life Cycle. They would cancel the tasks that did not apply to
document that step of the SDLC was not needed (this was done for consistency
and reporting). Once a CR or a set of CRs that made up a software release
were ready to move to production they would create a separate CR (in the PCR
view) with all of the development CRs related. Its only purpose was to be a
PCR and go through the review and approval process.

 

By doing it this way the Change Board was able to keep their own "bucket" of
requests and the developers/business analysts were able to have their own
"bucket" of requests but it all tied together. Because the two processes had
their own view it was easy to have different reporting, automation and set
different requirements based on the view that the request was submitted in
(captured that in a character field on submit).

 

Hope this helps,

Jason

 

  _____  

From: Action Request System discussion list(ARSList)
[mailto:[EMAIL PROTECTED] On Behalf Of Barbara Siebert
Sent: Tuesday, January 09, 2007 5:48 PM
To: [email protected]
Subject: Change Requests for Dev/QA and Production

 

A client has a process by which most of their changes go through
Development/QA before they are implemented in Production.  We believe we
have three options for this within Change Management 7:

1.      We submit two change requests, one for Dev/QA and one for Prod.  We
would create a button/link on the Navigation Pane of the Change Request form
to create a Production Change Request from the Dev/QA Change Request that
would copy the relevant fields from the Dev/QA Change Request into the
Production Change Request and relate the Dev/QA Change Request to Production
Change Request. 
2.      We use one Change Request and use the Status of Planning in Progress
for the actual planning, implementation in Development, and Testing in QA
and add these activities to the Status Reason Code for the Planning in
Progress Status. 
3.      We create a Parent Change Request and then create two Child Change
Requests, one for Dev/QA and one for Prod. 

Does anyone see an advantage to one method over the other?  Any other ideas?


 

Thanks for any and all insights.

Barb Siebert

QMX Support Services

__20060125_______________________This posting was submitted with HTML in
it___

_______________________________________________________________________________
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org ARSlist:"Where the 
Answers Are"

Reply via email to