Probably because it's a product that they use that's imbedded in
theirs....if they say it isn't them then ask them to identify the vendor of
the product that is a fault...and ask them if they are pressuring that
vendor to get it fixed or not.

  _____  

From: Action Request System discussion list(ARSList)
[mailto:[EMAIL PROTECTED] On Behalf Of Susan Palmer
Sent: Thursday, May 03, 2007 1:16 PM
To: arslist@ARSLIST.ORG
Subject: Re: Anyone else using CrystalDesk Report Scheduler PRO


** 
Great ... they told me the memory leak is not their product's issue.  Well
then why is it adding up within their product ???
 
Can't wait to hear the answer.
 
Thanks,
Susan

 
On 5/3/07, patrick zandi <[EMAIL PROTECTED]> wrote: 

** By the way, I send an email to crystaldesk folks, Told them I am
interested in the product (which I am) however will not buy it till they fix
the memory error. 


On 5/3/07, Susan Palmer <[EMAIL PROTECTED]
<mailto:[EMAIL PROTECTED]> > wrote: 

** 

Hi everyone,
 
I've been using the CrystalDesk Report Scheduler PRO for over a year now and
I find it a great timesaver.  I don't have a crystal server or report
server, but I do have many requests for daily reports that needed to be
automated.  I just create the Crystal report, put the report definition on
the server, and then user the scheduler to email the report at a specified
time, and day frequency desired.  Works great from that perspective.  It
uses the AR ODBC driver. 
 
Where I have a problem, is that there must be some kind of memory leak issue
at some point when the reports are generated.  Something is not closing
properly and although I've requested help from CrystalDesk little has been
forthcoming.  Therefore every other day right now I have to go in and 'exit'
the application and restart it to clear the memory usage it has accumulated.
Since the memory usage is on that application in the Task Manager I would
think it's the application not doing something it's supposed to.   When I
first start the application memory usage is about 7,220K, after one day of
report generation it is 519,124K !  
 
Is anyone else using the scheduler out there and if so, do you have the
problem too?  If you fixed it, how?  I have to add quite a few more reports
to the scheduler and that's going to mean a daily exit/restart.  
 
Thanks for your help,
Susan
 
ARS 5.1.2P1428
Oracle 9i2
(upgrade to 7.0.1P2, Oracle 10g scheduled for 5/11, 2nd time at it )
Windows 2003
3.62 GB Ram
CPU 3.06 GHz


 
Susan Palmer
ShopperTrak
200 W Monroe St  11th Floor
Chicago, IL  60606
Office:  312-529-5325
Cell:     312-502-7687
[EMAIL PROTECTED]
__20060125_______________________This posting was submitted with HTML in
it___ 




-- 
Patrick Zandi __20060125_______________________This posting was submitted
with HTML in it___ 


__20060125_______________________This posting was submitted with HTML in
it___ 

_______________________________________________________________________________
UNSUBSCRIBE or access ARSlist Archives at www.arslist.org ARSlist:"Where the 
Answers Are"

Reply via email to