Hi

 

Of course yes!

 

The master plan will work 100% only if you run it without any range on the items (or all the items from finished goods to the last components).

 

Anyway, I guess I can go home now *s*

 

To share my experience with you

 

Axapta master planning is amazing. The only problem is understanding the functionality. The classes behind master planning are absolutely flexible (same goes for production scheduling, inventmovement, inventupdate etc), it’s a fucking plain to understand these classes but once you know them then life becomes very easy *s*

 

I hope you have understood the concept of positive days and negative days?

 

Regards

 

harsh

 


From: ssb axapta [mailto:[EMAIL PROTECTED]
Sent: Thursday, 20 January 2005 5:05 p.m.
To: Axapta-Knowledge-Village@yahoogroups.com
Subject: RE: [Axapta-Knowledge-Village] RE: Attahment!

 

hi

 

it works atlast !!!!!

 

with one small adjustment.. (idiotic But !)

 

Run the master plan with Item-a,Item-B.

 

then it explodes correctly..

 

But this cant work fine since I will have so many levels in BOM in real time !!!!!!

 



Harry Deshpande <[EMAIL PROTECTED]> wrote:

Hi

 

Hm… that’s interesting.

 

Now can you again run MRP and check if the planned order of 55 is being changed again to 100?

 

Regards

 

harry

 


From: ssb axapta [mailto:[EMAIL PROTECTED]
Sent: Thursday, 20 January 2005 4:50 p.m.
To: Axapta-Knowledge-Village@yahoogroups.com
Subject: Re: [Axapta-Knowledge-Village] RE: Attahment!

 

Harry...

 

 

 Now it works in a strange way !!!!

 

I ran MRP ,and checked the results.It created PO for 100,Didnt consider the stock.Then I went to Inquiry - Requirement Profile - Update from Planned order screen.Now the order Qty is changed to 55 considering the stock !

 

I m lost completely !!!!!!!!!

 

For me ,the dynamic as well as static master plan is the same.So I dont think I shd get different results when I do a 'update'



Harry Deshpande
<[EMAIL PROTECTED]> wrote:

Hi

 

What u are looking at is a Dynamic plan and not static plan may be that’s why you have to click on update. But that has got nothing to do with ur current problem.

 

Now your planned date is 28/01 and todays date is  20/01 however your positive days are 7 days.

 

May be that is why your MRP is not considering on hand.

 

Go to the master plan , click override positiver days and put positive days as 30 and send me the screen shot again.

 

This is a setup issue and not a bug.

 

Regards

 

harsh

 


From: ssb axapta [mailto:[EMAIL PROTECTED]
Sent: Thursday, 20 January 2005 4:39 p.m.
To: Harry Deshpande
Subject: RE: Attahment!

 


check out this attachement.I am taking this from Item - Inquiry - net Reqmts.There is a catch heer.When I run MRP and check this screen,it doesnt show onhand .When I click "update"here in the screen ,then it adds the onhand line.So that means,on hand is NOT considered while running MRP.is it ? mmmm.. :)



Harry Deshpande
<[EMAIL PROTECTED]> wrote:

Hi

 

Also send me the screen shot on the net requirements screen but make sure the ‘setup’ tab is displayed on the header.

 

Regards

 

harsh

 

 

 

 

Harry Deshpande

Senior Consultant

CGNZ Middle Market Solutions

Ph +64 29 277 5133

Fax +64 9 358 1018

 

CGNZ Limited and its predecessor organisations (Cap Gemini Ernst & Young, and Ernst & Young Consulting) have a proud track record of market leadership and excellent service delivery in all areas of systems delivery both for New Zealand clients and in supporting regional and global projects.  CGNZ is a licensed affiliate of Cap Gemini S.A. (one of the world’s leading management consulting and IT services companies), wholly owned by NZ employee-shareholders, with over 150 IT professionals in our Auckland and Wellington offices.  Middle Market Solutions specialises in the implementation of business solutions for small corporate and middle market companies.  The core activity of our team is the implementation and support of Enterprise Resource Planning (ERP), Customer Relationship Management (CRM), E-Business solutions and related technologies from Microsoft Business Solutions.  Find out more about what we do at http://www.cgnz.com/middlemarketsolutions

 

CGNZ DISCLAIMER: This email and any attachments are confidential and intended exclusively for the person to whom the email is addressed. If you are not the intended recipient, do not read, copy, disclose or use the contents in any way. Please notify us immediately by return email and destroy the email and attachments. CGNZ does not accept any liability for any changes made to this email or attachments after sending by CGNZ. You must scan this email and attachments for viruses. The opinions expressed are not necessarily those of CGNZ. 

CGNZ accepts no liability for any loss, damage or consequence, whether caused by our own negligence or not, resulting directly or indirectly from the use of this email and attachments.

 


From: ssb axapta [mailto:[EMAIL PROTECTED]
Sent: Thursday, 20 January 2005 4:29 p.m.
To: Harry Deshpande
Subject: Attahment!

 

hi

 

sendin git to ur office id since yahoo geoup doesnt accept this large file.

 

check out ! after running MRP !

 

Now I know..it looks like a BUG !

 

I m finished !

 

:( sorry troubling u a lot ...

 

Yahoo! India Matrimony: Find your life partner online.

Yahoo! India Matrimony: Find your life partner online.



Sharing the knowledge on Axapta.

Yahoo! India Matrimony: Find your life partner online.

Sharing the knowledge on Axapta.



Sharing the knowledge on Axapta.

Yahoo! India Matrimony: Find your life partner online.

Sharing the knowledge on Axapta.




Sharing the knowledge on Axapta.



Yahoo! Groups Links

Reply via email to