1. Set up a "tools" work center group and make the jigs, inserts, 
and other necessary work centers under the group.
2. On the routings you would have a primary step of a machine and a 
secondary of the tool. Also possible would be a secordary 2 of a 
machine operator.

Hints: The tools WCG would have a resource type of Tool. The route 
step primary /secondary setting is the priority field. If using 
Operations scheduling then the WCG should only contain tools that 
are interchangeable (no mix of jigs AND inserts: jigs ONLY, etc.) 
and the route step should call the WCG rather than the specific WC. 
The primary operation determines the scheduling for the secondaries.

Example

Routing ABC
10 Primary Operation = Saw, WC = Saw1
10 Secondary 1 Operation = SJig, WC = Big Jig
10 Secondary 2 Operation = SOpr, WC = SOperator 1
20 Primary Clean, WC = Cleaning Station 1
30 Primary Inspect, WC = QA Inspector

Hope this helps.

Dick Howard
BKD Technologies
Indiana USA




------------------------ Yahoo! Groups Sponsor --------------------~--> 
Has someone you know been affected by illness or disease?
Network for Good is THE place to support health awareness efforts!
http://us.click.yahoo.com/Rcy2bD/UOnJAA/cosFAA/kGEolB/TM
--------------------------------------------------------------------~-> 

Sharing the knowledge on Axapta. 
Yahoo! Groups Links

<*> To visit your group on the web, go to:
    http://groups.yahoo.com/group/Axapta-Knowledge-Village/

<*> To unsubscribe from this group, send an email to:
    [EMAIL PROTECTED]

<*> Your use of Yahoo! Groups is subject to:
    http://docs.yahoo.com/info/terms/
 


Reply via email to