Dear hardi,
  If your production order has status reported as finished and remain status 
ended, you can actually reset. But if both are ended, you can’t. is that what 
you mean ?
   
  Rgds,
   
   
  Hardi <[EMAIL PROTECTED]> wrote:
          Dear all,

I have production order scheduled and started, with a job ID, for 
example I have planned 1 hour for that job.

Later on I updated the job 3 times via Job Card Journal.

Updated and posted 1st journal with 0.25 hour
Updated and posted 2nd journal with 0.5 hour
Updated and posted 3rd journal with 0.35 hour

Total is 1.1 hour (exceeded original plan of 1 hour).

The job status now is "Ended"

Then I need to post a correction job card journal, for example I 
updated and posted 4th journal with -0.5 hour.

So after 4th journal my total posted job hours = 0.6 hour (less than 
planned hour).

But when I look into my production job, the job status is still 
= "ended". Why is this? How to reset the job status back 
to "started"?

Thanks & regards

Hardi



         

 __________________________________________________
Do You Yahoo!?
Tired of spam?  Yahoo! Mail has the best spam protection around 
http://mail.yahoo.com 

[Non-text portions of this message have been removed]

Reply via email to