For all who have experience with Master Planning: I did the following and didn't work out!!!
I'm working with one plan strategy which is not static, and then proceeded as follows. 1- I run master scheduling specific for a certain item. 2- I made a forecast line. 3- I run forecast plan, and the result was good. 4- I run master plan with the net change methodÂ…But it didn't feel with the forecast demand as net change?!! The question is: is their something wrong with my data entry sequence OR forecast demand could never be felt with in the net change planning method? Note that when I run the master plan with the regeneration method it feels with the forecast. Regards;