try to run postsynchronization process after opening multiple clients.

On Thu, Oct 16, 2008 at 5:50 AM, Amit Jain <[EMAIL PROTECTED]> wrote:

>      Hi Guys,
>
> I am upgrading Axapta 3.0 SP3 to AX 4.0 SP2. Client has around 125 GB of
> data. During upgrade checklist, post synchronization is taking too much time
> and system totally goes into processing mode (sort of hangs). It is running
> almost for past 40 hours. Is there any way to fasten the process, or find
> the problem area. Also please tell me, is it ok, if i restart AOS and
> restart post syncronization process in middle of this process (when 60% of
> post synch has already been completed).
>
> Second issue is that for one of the table, some duplicate record is
> automatically getting created, during DBUpgradeTool exe execution.
>
> Please advice on these issues.
>
>
> Regards
> Amit
>
> ------------------------------
> Be the first one to try the new Messenger 9 Beta! Click 
> here..<http://in.rd.yahoo.com/tagline_messenger_7/*http://in.messenger.yahoo.com/win/>
>
> 
>

Reply via email to