Hi Trinadh,

Static Plan is updated when you run master scheduling at the same 
time (based on setting) Dynamics master plan is also updated.

Axapta net requirement takes Dynamics master plan data and days 
transactions to calculate real time net requirement.

For example: Master scheduling is executed on 01/01/2009 at 11 PM 
(this is the normal practice to run master scheduling when load on 
ERP is minimal). Now at 4 PM next day 01/02/2009 you want to see the 
net requirement of some item. Axapta takes base data from dynamics 
plan (which was updated at 11 PM on 01/01/2009 when master scheduling 
was run) and calculates the net requirement using transactions of 
01/02/2009.

Regards
Anil Sinha


--- In Axapta-Knowledge-Village@yahoogroups.com, "Trinadh Sura" 
<trin...@...> wrote:
>
> Hi all,
> What is the basic difference between the ststic and Dynamic master 
plans in Master Planning and how are they used in real time?
> what are the factors that influence or effect in selecting these 
plans?Regards,
> Trinadh
>