Hi Nitesh,

Thanks for the input.We already tried this.No luck :(

Best Regards
Chida and Pankaj

--- On Wed, 24/2/10, Nitesh Ranjan <[email protected]> wrote:

From: Nitesh Ranjan <[email protected]>
Subject: Re: [Axapta-Knowledge-Village] Ax2009 Upgrade Issue
To: [email protected]
Date: Wednesday, 24 February, 2010, 11:59 PM







 



  


    
      
      
      Hi Pankaj,
 
My take on this issue.
 
Stop the Presynch process and restart AX AOS and restart the Presynch process.
 
Let me know if it works.
 
Regards,
Nitesh Ranjan

--- On Wed, 2/24/10, Pankaj Kant <pankaj_kant@ infosys.com> wrote:


From: Pankaj Kant <pankaj_kant@ infosys.com>
Subject: [Axapta-Knowledge- Village] Ax2009 Upgrade Issue
To: "Axapta-Knowledge- vill...@yahoogro ups.com" <Axapta-Knowledge- 
vill...@yahoogro ups.com>
Date: Wednesday, February 24, 2010, 6:33 PM


  



Hi Every One
 
We are  upgrading Ax4.0 Sp1  instance to Ax 2009.I completed Application 
upgrade. Now I am stuck in DB upgrade ,presynch step(After 11 % completion ,its 
not 
proceeding further), I don’t Have any idea why it is not going ahead 
 
Please find below the steps which I had done so far :
 
1)Installed Ax 2009  (Pointed to Ax 4.0 DB ,service is not started at this 
point).
2)Installed Ax 2009 Sp1(service is not started at this point)
3)Copied the upgraded aods
4)Started the service
5)Completed the steps in Upgrade Check list till Presynch...
 
There are around 214 jobs in Presynch ,but after the 25th job its not 
proceeding and its not showing any error also..remaining jobs are moving to 
'Waiting' status.
 
I request the group members to throw some light on this issue
 
Thanks in Advance
 
Pankaj


      

    
     

    
    


 



  






      The INTERNET now has a personality. YOURS! See your Yahoo! Homepage. 
http://in.yahoo.com/

Reply via email to