Hi All,

I have updated STIP-30 with proposed phases, task checklists, and
links to the existing tracking and implementation
work:https://github.com/apache/seatunnel/issues/11364

The proposed sequence is:
1. Internal reporting foundation (#11512), with its scope unchanged.
2. MySQL validation, followed by parallel snapshot and freshness coverage.
3. Checkpoint, restore and recovery observability, coordinating with
the related #11947 failover harness.
4. PostgreSQL and multi-source validation.
5. Additive job-detail API and bounded metrics.
6. Performance, compatibility, stability and documentation gates,
starting alongside validation.

The first MySQL validation slice is now a dependent draft
PR:https://github.com/apache/seatunnel/pull/12137

It checks real source/sink data and naturally collected progress
reports. The focused scenario passed twice on each of Java 8 and 11;
broader CI and later scenarios remain open. No public API or metrics
are added.

The updated contract separates per-field value quality from report
freshness and does not infer a stall from an unchanged offset.
Enumerator collection is coordinator-owned, but execution may be on
another member.

Could you review the phase boundaries and remaining stabilization
gates, particularly checkpoint/restore semantics and validation of
both position families before freezing the public contract? These
remain proposed steps, not a release commitment or a claim of full
design acceptance.

I will keep agreed decisions and linked work recorded on the STIP.
Thanks all for your time and support

Thanks,
Goutam