Andy,

Should we look at committing the tool in HBASE-12808 and perhaps opening a
separate issue around getting it into the release profile? 0.98 might be a
good place to sort that out before the compatibility policy officially
needs to be enforced in 1.0+.

-Dima

On Monday, January 19, 2015, Andrew Purtell <[email protected]> wrote:

> Tests are looking better now. We are far enough delayed so I plan to kick
> off the RC process on January 26 to get back to approximately end of month
> releases. Please let me know if you have any concerns.
>
> On Tue, Jan 13, 2015 at 9:49 AM, Andrew Purtell <[email protected]
> <javascript:;>> wrote:
>
> > The 0.98 RC is on hold. There are some test instabilities that would
> > prevent a successful release qualification. See HBASE-12843, HBASE-12846,
> > and HBASE-12847. HBASE-12843 was resolved but I'm watching for
> > reoccurrance. The others may be related (need to dig in more on 12846).
> > They are all broadly master / assignment manager issues.
> >
> >
> > On Sun, Jan 4, 2015 at 6:37 PM, Andrew Purtell <[email protected]
> <javascript:;>>
> > wrote:
> >
> >> Short dev period due to the holidays, but let's keep the release cadence
> >> more or less on track. Please let me know if you have any concerns.
> >>
> >> --
> >> Best regards,
> >>
> >>    - Andy
> >>
> >> Problems worthy of attack prove their worth by hitting back. - Piet Hein
> >> (via Tom White)
> >>
> >
> >
> >
> > --
> > Best regards,
> >
> >    - Andy
> >
> > Problems worthy of attack prove their worth by hitting back. - Piet Hein
> > (via Tom White)
> >
>
>
>
> --
> Best regards,
>
>    - Andy
>
> Problems worthy of attack prove their worth by hitting back. - Piet Hein
> (via Tom White)
>