I'm not sure I can glean the use case from what you're describing. What is it you're trying to do?
We have a project which is all one unit, and currently use reactor to build all the subprojects, some of which are dependant on each other. Some are JARs and some are WARs.
At the moment, you either build just one, or build them all. The thought I had was that if you build just one, based on a flag it could also build its dependencies, so you get a complete build for that one component, without building other subprojects that you aren't working on (even if they haven't changed, the reactor takes some time to check that).
eg.
finserv-webapp depends on portfolios and markets portfolios depends on retriever markets depends on retriever
So building war:webapp inside finserv-webapp should build portfolios, markets, retriever via the reactor first.
Just building portfolios.jar though would build only portfolios and retriever.
Does that make sense? Can you think of an alternative structure that would alleviate the need to do this?
Cheers, Brett