> > The dates for each phase would be as follows:
> >
> > End of Development : 2009-03-02
> > End of Feature Freeze : 2009-03-16
> > Release : 2009-03-27
> >   
> 
> This was the last set of dates Martin had put up for 0.5 release. I 
> suspect that
> it is still worth putting a 0.5 as quite a lot of fixes have 
> been made 
> since M4.
> 
> Are we still on for freeze on Monday?
> Feature Freeze     March  02nd
> RC                       March  23rd (and branch trunk)

I'd like to get the new build scheme in for M5, based on cmake - I'm
not sure I'll have a first cut in by Monday, but it would be next week
sometime. I think that in order for that to be in M5, though, we'll
need some group discussion after getting a chance to test drive it a
bit.

Thoughts?

-Steve


---------------------------------------------------------------------