Carl Trieloff wrote:

The dates for each phase would be as follows:

End of Development : 2009-03-02
End of Feature Freeze : 2009-03-16
Release : 2009-03-27

This was the last set of dates Martin had put up for 0.5 release. I suspect that it is still worth putting a 0.5 as quite a lot of fixes have been made since M4.

Are we still on for freeze on Monday?
Feature Freeze     March  02nd
RC                       March  23rd (and branch trunk)

In Martin's original mail he suggested a two week freeze on trunk (i.e. bug fixes only), with a branch being created after that (16th March) on which any remaining issues would be resolved.

Are you suggesting increasing that to three weeks (i.e. branching on 23rd)?

---------------------------------------------------------------------