Hi, I am trying to export a simple project plan from org to taskjuggler through org-taskjuggler.el. I cannot get the behavour I expect and need do some manual tweaks to get the taskjuggler file working. The questions are as follows, whereafter the test org-file that I attempt export and finally the tweaked taskjuggler file that I was expecting to see from the 'org-export-as-taskjuggler'. What am I doing wrong?
1) The 'end' date specified in the ':taskjuggler_project' base is ignored and the default 280d is used. Because the project duration is long this throws an error. The 'start' date however seems properly picked up. 2) The 'task_id' fields are not exported properly. 3) The 'precedes' property is not exported at all Taskjuggler version is 2.4.3 org version is 7.7. Thanks, J # ORG testfile follows------------------ #+STARTUP: hidestars #+STARTUP: outline * Assessment findings (electrical) :taskjuggler_project: :PROPERTIES: :start: 2011-06-01 :end: 2014-06-01 :COLUMNS: %23ITEM(Task) %task_id %precedes %start %5Effort :END: ** Tasks *** Task A :PROPERTIES: :task_id: task_A :precedes: mils_A :Effort: 10d :END: *** Task B :PROPERTIES: :task_id: task_B :precedes: mils_B :Effort: 10d :END: *** Task C :PROPERTIES: :task_id: task_C :precedes: mils_B :Effort: 10d :END: ** Milestones *** Milestone A :PROPERTIES: :task_id: mils_A :start: 2012-01-01 :END: *** Milestone B :PROPERTIES: :task_id: mils_B :start: 2013-01-01 :END: # Tweaked taskjuggler file follows------------------ project assessment "Assessment findings (electrical)" "1.0" 2011-06-01 +2800d { } shift s40 "Part time shift" { workinghours wed, thu, fri off } resource jim "jim" { } task assessment "Assessment findings (electrical)" { purge allocations allocate jim start 2011-06-01 end 2014-06-01 task tasks "Tasks" { task task_a "Task A" { effort 80.0h precedes !!milestones.mils_a } task task_b "Task B" { effort 80.0h precedes !!milestones.mils_b } task task_c "Task C" { effort 80.0h precedes !!milestones.mils_b } } task milestones "Milestones" { task mils_a "Milestone A" { milestone start 2012-01-01 } task mils_b "Milestone B" { milestone start 2013-01-01 } } } taskreport "Gantt Chart" { headline "Project Gantt Chart" columns hierarchindex, name, start, end, effort, duration, completed, chart timeformat "%Y-%m-%d" hideresource 1 loadunit shortauto } resourcereport "Resource Graph" { headline "Resource Allocation Graph" columns no, name, utilization, freeload, chart loadunit shortauto sorttasks startup hidetask ~isleaf() } -- Johnny