On 12/10/14 10:34, Stefan Schmidt wrote:
> Hello.
>
> Greetings from EFL Dev Day!
>
> During my release status talk I mentioned a small change I would like to
> change for future releases.
>
> The feedback was positive so I want to bring it up here for a wider
> audience.
>
> What I propose is to merge the the two merge windows (pun intended) and
> move the first stabilization week towards the end and merge it with the
> other three weeks.
>
> This would result in a way simpler schedule:
> 8 weeks development followed by 4 weeks stabilization
>
> Why?:
> --------
> o Seen people struggle with what to commit when
> o Many people keep comitting in the first stabilization week like they
> do during the merge windows
> o Reduced schedule complexity. Down from three context switches to one
> o More natural devlopment (dev -> debug -> fix)
> o The extra week at the end should help for testing
>
> Anyone opposed this change? If not I will going to try it with 1.12
Obviously this should have been 1.13.

regards
Stefan Schmidt


------------------------------------------------------------------------------
Meet PCI DSS 3.0 Compliance Requirements with EventLog Analyzer
Achieve PCI DSS 3.0 Compliant Status with Out-of-the-box PCI DSS Reports
Are you Audit-Ready for PCI DSS 3.0 Compliance? Download White paper
Comply to PCI DSS 3.0 Requirement 10 and 11.5 with EventLog Analyzer
http://p.sf.net/sfu/Zoho
_______________________________________________
enlightenment-devel mailing list
enlightenment-devel@lists.sourceforge.net
https://lists.sourceforge.net/lists/listinfo/enlightenment-devel

Reply via email to