Hi James and Tona,

I'm wondering if you might be able to lend a hand with preparations for Engage 
0.3 quality assurance testing. Justin is pretty heads-down with development 
tasks, so I don't think he's going to have a chance to create all of the test 
plans we need to have in place before we start the QA phase on February 16. 

I'm wondering if you two are willing to help create these test plans, with some 
advice and moral support from Justin and crew as needed? Ideally, we'll try to 
get these finished by late next week so we have time to refine them before QA 
actually starts.

Sam is working on a screenreader-specific QA test plan as well, so it'd be 
worth syncing up everyone on this as well.

Let me know what you think,

Colin

---
Colin Clark
Technical Lead, Fluid Project
http://fluidproject.org

_______________________________________________________
fluid-work mailing list - [email protected]
To unsubscribe, change settings or access archives,
see http://fluidproject.org/mailman/listinfo/fluid-work

Reply via email to