Please let me know if I can be of any assistance with this.
Thanks,
Alison
On Feb 11, 2010, at 12:14 PM, Sambhavi Chandrashekar wrote:
Thank you, James. I will look into that and check with what I have.
Will email you for assistance with integration.
Sam
On Thu, Feb 11, 2010 at 12:10 PM, James William Yoon <[email protected]
> wrote:
Hi Sam,
Tona and I have completed writing our first draft of the QA test
plans, found under "Fluid Engage 0.3" on the right side here: http://wiki.fluidproject.org/display/fluid/Testing+Fluid+Components
Let us know where you're at with yours, and how we can assist you in
integrating the accessibility test plans into there. (QA testing
begins on Tuesday)
Cheers,
James
On Thu, Feb 4, 2010 at 1:50 PM, Sambhavi Chandrashekar <[email protected]
> wrote:
Hi James,
I will join you both on Wednesday next (Feb 10th). Will mail you on
Wed morning about what I get done up to that point. We can then
discuss how to align/integrate the tests with/into the main QA plan.
Sam
On Thu, Feb 4, 2010 at 11:56 AM, James William Yoon <[email protected]
> wrote:
I'm glad you brought this up. I had just pinged Justin about this
minutes ago. Tona and I are more than happy to lend our assistance
in writing the QA test plans. We'll work on this early next week.
Anyone else wanting to help us write the test plans and/or gain some
experience writing them is welcome to join us!
Cheers,
James
On Thu, Feb 4, 2010 at 11:25 AM, Colin Clark
<[email protected]> wrote:
Hi James and Tona,
I'm wondering if you might be able to lend a hand with preparations
for Engage 0.3 quality assurance testing. Justin is pretty heads-
down with development tasks, so I don't think he's going to have a
chance to create all of the test plans we need to have in place
before we start the QA phase on February 16.
I'm wondering if you two are willing to help create these test
plans, with some advice and moral support from Justin and crew as
needed? Ideally, we'll try to get these finished by late next week
so we have time to refine them before QA actually starts.
Sam is working on a screenreader-specific QA test plan as well, so
it'd be worth syncing up everyone on this as well.
Let me know what you think,
Colin
---
Colin Clark
Technical Lead, Fluid Project
http://fluidproject.org
_______________________________________________________
fluid-work mailing list - [email protected]
To unsubscribe, change settings or access archives,
see http://fluidproject.org/mailman/listinfo/fluid-work
_______________________________________________________
fluid-work mailing list - [email protected]
To unsubscribe, change settings or access archives,
see http://fluidproject.org/mailman/listinfo/fluid-work
_______________________________________________________
fluid-work mailing list - [email protected]
To unsubscribe, change settings or access archives,
see http://fluidproject.org/mailman/listinfo/fluid-work