[Of the last two remaining (known) major hurdles, one was cleared on Dec.
13 2018 (ref. point I&II. below).
So, now, the cost - including the financial pacage, if any, would be the
major consideration.

The article posted here draws our attention, also, to the safety aspects,
which affect human lives straightaway.
As regards the liability of the contractor it cannot but be linked to its
precise scope of work, which has to be finalised, if at all, based on the
techno-commercial offer on the table.
The primary responsibility, however, in any case, lies with the "operator".
That, arguably, makes things for the potential victims much simpler.
The "contractor"/"supllier", if at all, would be accountable to the
"operator".

I. <<On Friday 14th of December 2018, CGN and EDF announced, at a joint
press conference in Beijing, that unit 1 of Taishan nuclear power plant had
become the world's first EPR to enter into commercial operation. This last
milestone was reached on Thursday 13th of December 2018 after the final
statutory functional test of continuous operation at full power for 168
hours. The successful outcome of this test marks the achievement of all
prerequisite conditions for the reactor's safe operation.>>

(Ref.: <
https://globenewswire.com/news-release/2018/12/14/1667114/0/en/EDF-The-first-of-two-EPR-reactors-at-China-s-Taishan-nuclear-power-plant-enters-into-commercial-operation.html?fbclid=IwAR2VzG-_-k787URYLxqjChOeasX631DENVjdOc-NgMCDwbCbDTXv0EddLeo#.XBiDyJ1dTKQ.messenger
>.)

II. <<(Sekhar) Basu (the former chairman of the Atomic Energy Commission
and Secretary, Department of the Atomic Energy, who superannuated this
month) said there have been several factors that were hindering the power
plant, which includes the “reference plant”.
A reference plant is a functional power reactor and the Areva had then
cited a power reactor at Flamanville.
“That will only happen by 2020,” Basu said.
Since Areva, and now EDF, was bringing in a new technology, the Atomic
Energy Regulatory Board (AERB), the country nuclear watchdog, asked for a
reference plant.
“They have to give a techno-commercial offer that is feasible and tariffs
have to be viable,” Basu added.
Tariff has been a key concern, Basu and Sinha said as it has to be within
the acceptable limits before going ahead with the deal.>>

(Ref.: <
https://indianexpress.com/article/india/indo-french-nuclear-deal-10-years-after-its-signing-power-project-yield-little-success-5380153/
>.)

III. <<France submits techno-commercial offer for Jaitapur nuclear power
plant New Delhi: French company EDF has submitted a techno-commercial
proposal to the government for the Jaitapur Nuclear Power Plant (JNPP), in
a significant step towards the progress of the project, sources said. A
techno-commercial offer is an important step in the negotiations process as
it helps the two parties determine the cost of the project and tariff of
the electricity generated from it.
The offer comes less than a week after External Affairs Minister Sushma
Swaraj and French Foreign Minister Jean-Yves Le Drian agreed to expedite
work on the project.>>

(Ref.: <
https://energy.economictimes.indiatimes.com/news/power/france-submits-techno-commercial-offer-for-jaitapur-nuclear-power-plant/67224014
>.)]

https://www.thehindu.com/opinion/op-ed/jaitapur-a-risky-and-expensive-project/article25934123.ece?homepage=true&fbclid=IwAR1IUKmEVH8AH0zUQIEo0VK_UzYLEJ9WEXiiiLUJIAEUT3RlP_5uTW5PEJY

Jaitapur: A risky and expensive project

Suvrat Raju & M.V. Ramana

JANUARY 08, 2019 00:15 IST
UPDATED: JANUARY 08, 2019 00:12 IST

 “It is clear that electricity from the Jaitapur project will be more
expensive than many other sources of electricity.” People marching against
the nuclear power plant proposed at Jaitapur in Maharashtra's Konkan region
in Mumbai in 2011.Paul Noronha
“It is clear that electricity from the Jaitapur project will be more
expensive than many other sources of electricity.” People marching against
the nuclear power plant proposed at Jaitapur in Maharashtra's Konkan region
in Mumbai in 2011.Paul Noronha

*Unless the government is transparent about details, it will be engulfed in
yet another controversy*

In December, the French company Électricité de France (EDF) submitted a
“techno-commercial proposal” to the Indian government for the Jaitapur
nuclear power project in Maharashtra. The idea of importing six nuclear
European Pressurised Reactors (EPRs) was initiated by the United
Progressive Alliance government more than a decade ago, but the project had
made little progress due to concerns about the economics and safety of the
EPRs, local opposition, and the collapse of the initial French corporate
partner, Areva. Despite these problems, in the past few months, the Modi
government has taken several high-level steps towards actuating the project.

In March 2018, EDF and the Nuclear Power Corporation of India (NPCIL)
signed an “industrial way forward” agreement in the presence of Prime
Minister Narendra Modi and French President Emmanuel Macron. Last month,
after meeting the French Foreign Minister, Jean-Yves Le Drian, External
Affairs Minister Sushma Swaraj announced that “both countries are working
to start the Jaitapur project as soon as possible”. The urgency is
inexplicable as it comes before the techno-commercial offer has been
examined and as earlier questions about costs and safety remain unanswered.
Moreover, with the Indian power sector facing surplus capacity and a crisis
of non-performing assets (NPAs), a large investment in the Jaitapur project
is particularly risky.

Delays and cost increases
It is clear that electricity from the Jaitapur project will be more
expensive than many other sources of electricity, including solar and wind
power. Using international estimates of capital costs for EPRs from the
2010-2012 period, and after adjusting for cost savings in India, we had
shown in 2013 that first year tariffs from the project would be around ₹15
per kilowatt-hour (“Repeating Enron in Jaitapur”, June 21, The Hindu). Even
this figure must be revised upwards to account for the construction
experience with EPRs over the past five years. Across the world, EPRs have
experienced delays and cost increases. The first EPR entered commercial
operation in December 2018 at the Taishan site in China, five years later
than originally projected. Its final capital cost was estimated by industry
sources to be “40% over the original estimate”. The story in Europe is more
dramatic. The EPR at Flamanville in France, for example, went from an
expected start date of 2012 to 2020, and a cost estimate of €3.3 billion to
€10.9 billion. Two EPRs have been planned at Hinkley Point in the U.K. Even
before construction began, the estimated cost has risen significantly to
£20 billion (about ₹1.75 lakh crore). The British National Audit Office
assessed that the project “locked consumers into a risky and expensive
project with uncertain strategic and economic benefits.”

While nuclear costs have been rising, other low-carbon sources of
electricity, especially solar energy, have become cheaper. In 2010-11,
tariffs for solar photovoltaic (PV) projects under the National Solar
Mission were between ₹10.95 and ₹12.76 per unit. But several projects
approved under Phase II of the mission have been connected to the grid in
the last year with tariffs below ₹5 per unit. In recent auctions for solar
PV projects, winning tariff bids in the range of ₹2 to ₹2.50 per unit have
become routine.

The high capital costs of the EPRs are of particular concern because
power-generating capacity in India has grown faster than demand causing
projects to run into financial difficulties. In March 2018, the
parliamentary standing committee on energy listed 34 “stressed” projects,
including NPAs and “those which have the potential to become NPAs”, with a
cumulative outstanding debt of ₹1.74 lakh crore. In this context, the
government seems to be throwing caution to the winds by investing lakhs of
crores in the Jaitapur project. Because the NPCIL’s debts would ultimately
be underwritten by the Indian government, if the project encounters
financial difficulties, the costs would fall on Indian taxpayers.

Safety problems
In addition to the high costs, safety problems with the reactor design and
construction have emerged in several EPRs. The most serious of these
pertained to the pressure vessel, which is the key barrier that prevents
the spread of radioactive materials from the reactor. In April 2015, the
French nuclear safety regulator, Autorité Sûreté Nucléaire, announced that
some sections of the pressure vessel that the French Creusot Forge had
supplied to the Flamanville and Taishan reactors had too much carbon in the
steel. The Flamanville project was also found to have substandard welding
in the reactor’s pipes. The EPR at Olkiluoto in Finland encountered
problems with vibrations in the pipe that connects the primary coolant
system with the pressuriser, which maintains the pressure of the water
circulating in the reactor.

These safety concerns are exacerbated by India’s flawed nuclear liability
law. If and when completed, Jaitapur “will be the largest nuclear power
plant in the world”. In the event of an accident, the nuclear liability law
would require the public sector NPCIL to compensate victims and pay for
clean-up, while largely absolving EDF of responsibility.

The Indian law provides NPCIL with a limited opportunity to obtain
compensation from EDF for the “supply of equipment... with... defects... or
sub-standard services”. But the joint statement issued in March 2018
promises that the “enforcement of India’s rules” would be in accordance
with the international Convention on Supplementary Compensation for nuclear
damage, which severely limits the operator’s right of recourse. This raises
the disturbing possibility that the NPCIL may have promised not to exercise
its right to claim compensation from EDF as allowed by Indian law. In any
event, there is a “moral hazard” here: since EDF can escape with limited or
no consequences even after a severe accident, it has little material
incentive to maintain the highest safety standards, particularly if the
requirements of safety come into conflict with the imperative to lower
costs. Such pressures might be accentuated by EDF’s poor financial state.

The Modi-Macron statement “emphasized the need for the project to generate
cost-effective electricity”. It is hard to see how this is possible. To
begin with, the government must answer several specific questions: how much
will the entire project cost, who will be accountable for cost increases
and delays, and what is the precise arrangement that the government has
reached with France on liability? Unless it is transparent about these
details, the Modi government may well find itself engulfed in yet another
controversy involving overpriced French equipment.

Suvrat Raju and M.V. Ramana are physicists associated with the Coalition
for Nuclear Disarmament and Peace, and currently based in Bengaluru and
Vancouver, respectively. Views are personal
-- 
Peace Is Doable

-- 
You received this message because you are subscribed to the Google Groups 
"Green Youth Movement" group.
To unsubscribe from this group and stop receiving emails from it, send an email 
to greenyouth+unsubscr...@googlegroups.com.
To post to this group, send an email to greenyouth@googlegroups.com.
Visit this group at https://groups.google.com/group/greenyouth.
For more options, visit https://groups.google.com/d/optout.

Reply via email to