https://issues.apache.org/jira/browse/HBASE-21375?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=16666384#comment-16666384
 ] 

Duo Zhang commented on HBASE-21375:
-----------------------------------

Any other concerns? [~stack] [~allan163] Thanks.

> Revisit the lock and queue implementation in MasterProcedureScheduler
> ---------------------------------------------------------------------
>
>                 Key: HBASE-21375
>                 URL: https://issues.apache.org/jira/browse/HBASE-21375
>             Project: HBase
>          Issue Type: Sub-task
>          Components: proc-v2
>            Reporter: Duo Zhang
>            Assignee: Duo Zhang
>            Priority: Major
>             Fix For: 3.0.0, 2.2.0
>
>         Attachments: HBASE-21375-UT.patch, HBASE-21375-UT2.patch, 
> HBASE-21375-v1.patch, HBASE-21375-v2.patch, HBASE-21375.patch
>
>
> The problem for the old implementation is that we will only check the first 
> procedure in a queue to see if it could run, if it can not, we will remove 
> the queue from run queue. So when adding procedure to the scheduler, we have 
> to try hard to put the procedure which can be executed in front of the queue, 
> if there are corner cases where we fail to do so, it will likely lead to a 
> dead lock, that's why we have the tricky code when loading procedures and try 
> to add them into the scheduler, and also lots of 'if' in the doAdd method of 
> MasterProcedureScheduler. But this is still not enough to make things right, 
> so finally [~allan163] and I decided to change the logic in doPoll method, 
> where we use a loop to find whether there is a procedure can be executed, not 
> only the first one.



--