*Update: Lincoln School Project*
*Honoring our History, Building Our Future*

Inside the Learning Commons

Although all preK-8 students will be in the renovated school this fall, the
School Building Committee anticipates that big work (installation of PV
panels and connectivity) and small (punch list items) will continue on the
Lincoln School campus for about another year. Here are some major
milestones to watch for:

   - Furniture and equipment for grades K - 4 will move out of the modular
   school between June 22 and July 3.
   - The modular units will be removed from campus between July 25 and
   August 12.
   - About 25% of the photovoltaic (PV) panels are expected to arrive soon.
   Supply chain issues have slowed down delivery. Installation will begin on
   the Middle School gym.
   - All the PV panels should be installed and on line by next
   spring/summer.

The project team and SBC continue to closely monitor supply chain issues,
schedule, and budget.

Click here
<https://lincolnsbc.org/wp-content/uploads/2022/06/2022-06-15-LPS-SBC-Presentation-DPI.pdf>
for
the slide deck from this past week's meeting, and here
<https://lincolnsbc.org/galleries/project-photos-june-2022/> for the June
photo gallery.
-- 
The LincolnTalk mailing list.
To post, send mail to Lincoln@lincolntalk.org.
Search the archives at http://lincoln.2330058.n4.nabble.com/.
Browse the archives at https://pairlist9.pair.net/mailman/private/lincoln/.
Change your subscription settings at 
https://pairlist9.pair.net/mailman/listinfo/lincoln.

Reply via email to