The Time required for the entire project is a read-only property. It shows the sum of the Time required of all subtasks of the project.
If you want to set Time required values for the project or its subtasks, you can do it in the "Effort" section. On Tuesday, September 29, 2020 at 12:14:36 AM UTC+3 tsogra...@gmail.com wrote: > I have used this variable in the past, but now I am not able to use it. > For a given task, I tag it as a Project, and then the two variables "Time > Required For the Project" Max and Min appear in black instead of grey, but > when I go to input a value it doesn't let me. > > Now it seems that these variables are simply meant to roll up the 'Time > Required" by their sub tasks, but how do I input a Time Required? > > I see that I have older tasks (not projects) where I inputted Time > Required, but now for non-projects those values are greyed out and empty in > the Properties box, even though they show up in my View > > Any insights would be appreciated. > -- You received this message because you are subscribed to the Google Groups "MyLifeOrganized" group. To unsubscribe from this group and stop receiving emails from it, send an email to mylifeorganized+unsubscr...@googlegroups.com. To view this discussion on the web visit https://groups.google.com/d/msgid/mylifeorganized/0a0f1eff-7bc5-4624-8416-87c97f0e5f85n%40googlegroups.com.