I went through all 1.0 items and changed those to 1.1 that I think are not that important. There are 24 issues left that I think need to be fixed before we can declare 1.0 final. Among them are a lot of debugger problems likely related to closures that may be hard to fix.
Peter, one issue is "fix all failing tests". So we really want to "be green" for the release! Two other things we need to prepare is the one-click image (I think Marcus said he will look into this) and a secondary update stream that allows us to push maintenance changes to 1.0.x at the same time as we work on 1.1. So, there is still quite some work left... Adrian On Sep 4, 2009, at 08:52 , Stéphane Ducasse wrote: > Hi all > > I suggest the following: > we go over the bug tracker and move to 1.1 all the issues that are > not showstopper > and we declare pharo 1.0 done > and we open pharo 1.1 alpha > > Does it make sense to you? > Stef > > _______________________________________________ > Pharo-project mailing list > [email protected] > http://lists.gforge.inria.fr/cgi-bin/mailman/listinfo/pharo-project _______________________________________________ Pharo-project mailing list [email protected] http://lists.gforge.inria.fr/cgi-bin/mailman/listinfo/pharo-project