Cooper Nuclear Station has the following question concerning BWR 100% power 
steam affected area surveys.

CNS currently performs a 100% power survey post outage and accumulates 
approximately 200 mrem, and the question was posed do we need to perform this 
survey?  At what frequency does you plant perform steam affected area 100% 
power surveys?  Do you post the areas survey required prior to entry or do you 
do surveys on some frequency (semi-annual, annual, post outage 100% power?)

Jeremy Bebb
Staff Health Physicist
Cooper Nuclear Station
(402) 825-5026