Mark-
The 2018 IFC and IRC both state "Pathways shall be located in areas with
minimal obstructions, such as vent pipes, conduit or mechanical
equipment."

It must be permanently marked "WARNING PHOTOVOLTAIC POWER SOURCE" in
accordance with 690.31(G)(3) as well.


Brian Mehalic
NABCEP Certified Solar PV Installation Professionalâ„¢ R031508-59
520.204.6639

Solar Energy International
http://www.solarenergy.org

SEI Professional Services
http://www.seisolarpros.com


On Thu, Apr 19, 2018 at 11:02 AM, Mark Frye <ma...@berkeleysolar.com> wrote:

> Folks,
>
> I have a 3 foot "walkway" on a roof pitch and between two separate arrays,
> as required.
>
> Is there anything that prevents me from running a conduit between the two
> arrays, across the "walkway"?
>
> Thanks,
>
> Mark Frye
>
> _______________________________________________
> List sponsored by Redwood Alliance
>
> List Address: RE-wrenches@lists.re-wrenches.org
>
> Change listserver email address & settings:
> http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org
>
> List-Archive: http://www.mail-archive.com/re-wrenches@lists.re-wrenches.or
> g/maillist.html
>
> List rules & etiquette:
> www.re-wrenches.org/etiquette.htm
>
> Check out or update participant bios:
> www.members.re-wrenches.org
>
>
_______________________________________________
List sponsored by Redwood Alliance

List Address: RE-wrenches@lists.re-wrenches.org

Change listserver email address & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

List-Archive: 
http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html

List rules & etiquette:
www.re-wrenches.org/etiquette.htm

Check out or update participant bios:
www.members.re-wrenches.org

Reply via email to