Tim Chase writes:
>I have several events that fall on the Nth weekday of the (e.g 1st
>Saturday) and when they get bumped by an OMIT, they usually move back
>one week (so instead of July 4th of 2020, it would move to July 11th
>of 2020).  Is there a way to specify that the BEFORE/AFTER should
>shift things by a certain number of days other than one?

I don't know if this will help you, but I use this:

rem thu 22 OMIT WED BEFORE msg DDS patches

for a Thursday event that, if Thursday is a holiday, moves back to Tuesday.

You might need to OMIT every day except your specific day.

--hymie!     http://lactose.homelinux.net/~hymie    [email protected]
_______________________________________________
Remind-fans mailing list
[email protected]
https://dianne.skoll.ca/mailman/listinfo/remind-fans
Remind is at https://dianne.skoll.ca/projects/remind/

Reply via email to