[JBoss-dev] Re: Toward JBoss v4.0.4.GA - Part 1 - JIRA tasks

2006-04-07 Thread Alexey Loubyansky

Are the J2EE TCK tests part of the QA procedure before the release?

Dimitris Andreadis wrote:

When we started work on 4.0.4 we had 300+ issues ahead of us, now after
2 candidate releases we are down to around 80, which is quite an
achievement, but still a significant amount of work is left for the
final (GA) release.

The current target date is 26th/April which includes Easter and is just
3 weeks ahead of us. This gives roughly 2 weeks of bug fixing and 1 week
of integration testing. New features shouldn't be introduced at this
point.

Please take a look at the issues assigned to you and resolve/defer in
time:
http://jira.jboss.com/jira/secure/IssueNavigator.jspa?mode=hiderequestI
d=12310181

Take a look at the unassigned ones and help:
http://jira.jboss.com/jira/secure/IssueNavigator.jspa?mode=hiderequestI
d=12310482

The current breakout is roughly shown below. 


NoComponent 3
Build   2
Clustering  7
CMP 13
Deployment  3
Documentation   1  (+ 6 dependencies)
EJB 10 (6 unassigned)
Hibernate   1
IIOP2
Installer   5 (5 unassigned)
JCA 1
JMX 5 (1 unassigned)
Logging 1
Management  2
Naming  1
Other   1
Remoting6
Security6 (1 unassigned)
System  1
Testsuite   5 (1 unassigned)
Tomcat  6
WebServices 3
XML 1




---
This SF.Net email is sponsored by xPML, a groundbreaking scripting language
that extends applications into web and mobile media. Attend the live webcast
and join the prime developer group breaking into this new coding territory!
http://sel.as-us.falkag.net/sel?cmd=lnkkid=110944bid=241720dat=121642
___
JBoss-Development mailing list
JBoss-Development@lists.sourceforge.net
https://lists.sourceforge.net/lists/listinfo/jboss-development


[JBoss-dev] RE: Toward JBoss v4.0.4.GA - Part 1 - JIRA tasks

2006-04-07 Thread Dimitris Andreadis

It's not planned. Some do individual TCK testing (e.g. WS).

 -Original Message-
 From: Alexey Loubyansky 
 Sent: 07 April, 2006 15:42
 To: Dimitris Andreadis
 Cc: jboss-development
 Subject: Re: Toward JBoss v4.0.4.GA - Part 1 - JIRA tasks
 
 Are the J2EE TCK tests part of the QA procedure before the release?
 
 Dimitris Andreadis wrote:
  When we started work on 4.0.4 we had 300+ issues ahead of us, now 
  after
  2 candidate releases we are down to around 80, which is quite an 
  achievement, but still a significant amount of work is left for the 
  final (GA) release.
  
  The current target date is 26th/April which includes Easter and is 
  just
  3 weeks ahead of us. This gives roughly 2 weeks of bug fixing and 1 
  week of integration testing. New features shouldn't be 
 introduced at 
  this point.
  
  Please take a look at the issues assigned to you and 
 resolve/defer in
  time:
  
 http://jira.jboss.com/jira/secure/IssueNavigator.jspa?mode=hidereques
  tI
  d=12310181
  
  Take a look at the unassigned ones and help:
  
 http://jira.jboss.com/jira/secure/IssueNavigator.jspa?mode=hidereques
  tI
  d=12310482
  
  The current breakout is roughly shown below. 
  
  NoComponent 3
  Build   2
  Clustering  7
  CMP 13
  Deployment  3
  Documentation   1  (+ 6 dependencies)
  EJB 10 (6 unassigned)
  Hibernate   1
  IIOP2
  Installer   5 (5 unassigned)
  JCA 1
  JMX 5 (1 unassigned)
  Logging 1
  Management  2
  Naming  1
  Other   1
  Remoting6
  Security6 (1 unassigned)
  System  1
  Testsuite   5 (1 unassigned)
  Tomcat  6
  WebServices 3
  XML 1
  
 


---
This SF.Net email is sponsored by xPML, a groundbreaking scripting language
that extends applications into web and mobile media. Attend the live webcast
and join the prime developer group breaking into this new coding territory!
http://sel.as-us.falkag.net/sel?cmd=lnkkid0944bid$1720dat1642
___
JBoss-Development mailing list
JBoss-Development@lists.sourceforge.net
https://lists.sourceforge.net/lists/listinfo/jboss-development


[JBoss-dev] Re: Toward JBoss v4.0.4.GA - Part 1 - JIRA tasks

2006-04-07 Thread Alexey Loubyansky

That's what I was afraid of.

Dimitris Andreadis wrote:

It's not planned. Some do individual TCK testing (e.g. WS).


-Original Message-
From: Alexey Loubyansky 
Sent: 07 April, 2006 15:42

To: Dimitris Andreadis
Cc: jboss-development
Subject: Re: Toward JBoss v4.0.4.GA - Part 1 - JIRA tasks

Are the J2EE TCK tests part of the QA procedure before the release?

Dimitris Andreadis wrote:
When we started work on 4.0.4 we had 300+ issues ahead of us, now 
after
2 candidate releases we are down to around 80, which is quite an 
achievement, but still a significant amount of work is left for the 
final (GA) release.


The current target date is 26th/April which includes Easter and is 
just
3 weeks ahead of us. This gives roughly 2 weeks of bug fixing and 1 
week of integration testing. New features shouldn't be 
introduced at 

this point.

Please take a look at the issues assigned to you and 

resolve/defer in

time:


http://jira.jboss.com/jira/secure/IssueNavigator.jspa?mode=hidereques

tI
d=12310181

Take a look at the unassigned ones and help:


http://jira.jboss.com/jira/secure/IssueNavigator.jspa?mode=hidereques

tI
d=12310482

The current breakout is roughly shown below. 


NoComponent 3
Build   2
Clustering  7
CMP 13
Deployment  3
Documentation   1  (+ 6 dependencies)
EJB 10 (6 unassigned)
Hibernate   1
IIOP2
Installer   5 (5 unassigned)
JCA 1
JMX 5 (1 unassigned)
Logging 1
Management  2
Naming  1
Other   1
Remoting6
Security6 (1 unassigned)
System  1
Testsuite   5 (1 unassigned)
Tomcat  6
WebServices 3
XML 1






---
This SF.Net email is sponsored by xPML, a groundbreaking scripting language
that extends applications into web and mobile media. Attend the live webcast
and join the prime developer group breaking into this new coding territory!
http://sel.as-us.falkag.net/sel?cmd=lnkkid=110944bid=241720dat=121642
___
JBoss-Development mailing list
JBoss-Development@lists.sourceforge.net
https://lists.sourceforge.net/lists/listinfo/jboss-development