> Is there any way, or is it possible, to get more than one scheduled
event
> to occur on
o:allen.barth@;DB.COM]
Sent: Thursday, November 14, 2002 12:57 PM
To: [EMAIL PROTECTED]
Subject: dsmcad scheduler and multiple tasks
Hello list.
Is there any way, or is it possible, to get more than one scheduled event
to occur on a client during the same time (or overlapping times) in which
One solution will be to have the TSM server kick off one and the OS to kick
off the other one via crontab or any scheduler program...
Allen Barth
cc:
Sent by: "ADSM: Subject: dsmcad schedule
could u give the sample script
regards
Raghu
Thomas Denier
cc:
Sent by: "ADSM: Subject: Re: dsmcad scheduler and
multiple
Dist Stor Manager"tasks
<[EMAIL P
---> I don't know whether this second approach can be modified to work with
dsmcad
dsmcad -optfile=
ought to help. You have to be careful web ports in different dsm.sys
stanzas not to overlap.
Zlatko Krastev
IT Consultant
> Is there any way, or is it possible, to get more than one scheduled event
> to occur on a client during the same time (or overlapping times) in which
> the scheduler is controlled via dsmcad? I don't remember if this was
> even possible using 'dsmc sched'.
The 'dsmc sched' mechanism behaved ju
Hello list.
Is there any way, or is it possible, to get more than one scheduled event
to occur on a client during the same time (or overlapping times) in which
the scheduler is controlled via dsmcad? I don't remember if this was
even possible using 'dsmc sched'.
Example:
At midnight a schedule