Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance -, 15th August

2017-08-13 Thread Glen Turner
Mark Newton wrote: > It should be made completely clear during customer onboarding that the > facility operator can temporarily shut down a power feed at any time. > Advance warning should be desirable but optional. Whilst I have some sympathy for Mark's position given the preceding discussion,

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance -, 15th August

2017-08-12 Thread Jared Hirst
ared.hi...@serversaustralia.com.au> From: AusNOG on behalf of Mark Smith Sent: Saturday, August 12, 2017 12:53:41 PM To: Mark Newton Cc: ; ausnog-requ...@lists.ausnog.net; c...@cpkws.com.au Subject: Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance -, 15th Augu

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance -, 15th August

2017-08-11 Thread Mark Smith
pecially during those times. > > Kindest Regards, > Nathan Brookfield (VK2NAB) > > -Original Message- > From: AusNOG [mailto:ausnog-boun...@lists.ausnog.net] On Behalf Of Chad Kelly > Sent: Thursday, August 10, 2017 2:54 PM > To: ausnog@lists.ausnog.net; ausnog-requ...@lists.ausnog.n

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance -, 15th August

2017-08-11 Thread Shaun McGuane
NXT) www.nextdc.com<http://www.nextdc.com> From: Shaun McGuane [mailto:sh...@rackcentral.com] Sent: Friday, 11 August 2017 4:58 PM To: Simon Cooper mailto:simon.coo...@nextdc.com>> Cc: ausnog@lists.ausnog.net<mailto:ausnog@lists.ausnog.net> Subject: RE: [AusNOG] NextDC Melbourne - Sch

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance -, 15th August

2017-08-11 Thread Matt Perkins
s.ausnog.net ; ausnog-requ...@lists.ausnog.net ; Chad Kelly *Subject:* Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance -, 15th August As someone who has run colo facilities before: It should be made completely clear during customer onboarding that the faci

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance -, 15th August

2017-08-11 Thread Jared Hirst
_ From: Chad Kelly Sent: Friday, August 11, 2017 10:34:57 PM To: Sam Silvester Cc: Jared Hirst; Mark Newton; Nathan Brookfield; ausnog@lists.ausnog.net; ausnog-requ...@lists.ausnog.net Subject: Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance -, 15th August Hi I did post the following l

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance -, 15th August

2017-08-11 Thread Chad Kelly
o:* Nathan Brookfield *Cc:* ausnog@lists.ausnog.net ; ausnog-requ...@lists.ausnog.net ; Chad Kelly *Subject:* Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance -, 15th August As someone who has run colo facilities before: It should be made completely cle

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance -, 15th August

2017-08-11 Thread Sam Silvester
> on > behalf of Mark Newton > > *Sent:* Friday, August 11, 2017 4:54:10 AM > *To:* Nathan Brookfield > *Cc:* ausnog@lists.ausnog.net > ; > ausnog-requ...@lists.ausnog.net > ; Chad > Kelly > *Subject:* Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance -,

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance -, 15th August

2017-08-11 Thread Chad Kelly
7 4:54:10 AM *To:* Nathan Brookfield *Cc:* ausnog@lists.ausnog.net; ausnog-requ...@lists.ausnog.net; Chad Kelly *Subject:* Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance -, 15th August As someone who has run colo facilities before: It should be made completely clear during cu

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance -, 15th August

2017-08-10 Thread Shaun McGuane
usnog@lists.ausnog.net; ausnog-requ...@lists.ausnog.net; Chad Kelly Subject: Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance -, 15th August Mark, Totally agree. I would just like to know what law Simon was referring too? Regards, Jared Hirst Servers Australia Pty Ltd Phone: +61 2

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance -, 15th August

2017-08-10 Thread Jared Hirst
behalf of Mark Newton Sent: Friday, August 11, 2017 4:54:10 AM To: Nathan Brookfield Cc: ausnog@lists.ausnog.net; ausnog-requ...@lists.ausnog.net; Chad Kelly Subject: Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance -, 15th August As someone who has run colo facilities before: It sho

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August

2017-08-10 Thread Mark Newton
r computer. > > > From: AusNOG [mailto:ausnog-boun...@lists.ausnog.net > <mailto:ausnog-boun...@lists.ausnog.net>] On Behalf Of Matthew Smee > Sent: Thursday, 10 August 2017 12:00 PM > To: ausnog@lists.ausnog.net <mailto:ausnog@lists.ausnog.net> > Subject: Re: [

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance -, 15th August

2017-08-10 Thread Mark Newton
et] On Behalf Of Chad Kelly > Sent: Thursday, August 10, 2017 2:54 PM > To: ausnog@lists.ausnog.net; ausnog-requ...@lists.ausnog.net > Subject: Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance -, 15th > August > > > > On 8/10/2017 10:13 AM, ausnog-requ...@l

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August

2017-08-10 Thread James Hodgkinson
law the requires you >> to shut down boards.>> >> Regards, >> >> Jared Hirst >> Servers Australia Pty Ltd >> Phone: +61 2 8115 8801 >> Email: jared.hi...@serversaustralia.com.au >> >> *From:* AusNOG on behalf of Simon >>

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance -, 15th August

2017-08-09 Thread Chad Kelly
imes. Kindest Regards, Nathan Brookfield (VK2NAB) -Original Message- From: AusNOG [mailto:ausnog-boun...@lists.ausnog.net] On Behalf Of Chad Kelly Sent: Thursday, August 10, 2017 2:54 PM To: ausnog@lists.ausnog.net; ausnog-requ...@lists.ausnog.net Subject: Re: [AusNOG] NextDC Melbourne

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance -, 15th August

2017-08-09 Thread Peter Tiggerdine
times. >> >> Kindest Regards, >> Nathan Brookfield (VK2NAB) >> >> -Original Message- >> From: AusNOG [mailto:ausnog-boun...@lists.ausnog.net] On Behalf Of Chad >> Kelly >> Sent: Thursday, August 10, 2017 2:54 PM >> To: ausnog@lists.ausn

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August

2017-08-09 Thread Sam Silvester
by replying to it and then > delete the message from your computer. > > > > > > *From:* AusNOG [mailto:ausnog-boun...@lists.ausnog.net > ] *On > Behalf Of *Matthew Smee > *Sent:* Thursday, 10 August 2017 12:00 PM > *To:* ausnog@lists.ausnog.net > > *S

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August

2017-08-09 Thread Jared Hirst
To: Jared Hirst Cc: Simon Cooper; ausnog@lists.ausnog.net Subject: Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August I also am unaware of such a law. Simon, can you advise? I'm told in QLD that live works are not permitted, but I am in SA so I have not really bot

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August

2017-08-09 Thread Sam Silvester
be happy to discuss these works with anyone - probably best offline > or on the phone - but trust me when I say we are doing our absolute best to > keep your data centre operating safely and reliably for many years to come. > > Thanks, > Simon > COO, NEXTDC > > -Original

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th, August

2017-08-09 Thread Chad Kelly
On 8/10/2017 2:47 PM, ausnog-requ...@lists.ausnog.net wrote: Maybe it could be helpful to the Ausnog list to point us to that law you refer too? As I personally have never heard or seen this done in any DC in Australia, or the world in the past 15 years I have been housing gear in Data Centr

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance -, 15th August

2017-08-09 Thread Chad Kelly
ists.ausnog.net; ausnog-requ...@lists.ausnog.net Subject: Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance -, 15th August On 8/10/2017 10:13 AM, ausnog-requ...@lists.ausnog.net wrote: From the latest update today, It appears that most of the works are being postponed for the time being

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance -, 15th August

2017-08-09 Thread Nathan Brookfield
2017 2:54 PM To: ausnog@lists.ausnog.net; ausnog-requ...@lists.ausnog.net Subject: Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance -, 15th August On 8/10/2017 10:13 AM, ausnog-requ...@lists.ausnog.net wrote: > From the latest update today, It appears that most of the works are >

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance -, 15th August

2017-08-09 Thread Chad Kelly
On 8/10/2017 10:13 AM, ausnog-requ...@lists.ausnog.net wrote: From the latest update today, It appears that most of the works are being postponed for the time being Not all devices within racks support 2 feeds and planning is involved with these devices, which is why it is crucial to receiv

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August

2017-08-09 Thread Matt Perkins
a.com.au> *From:* AusNOG on behalf of Simon Cooper *Sent:* Thursday, August 10, 2017 8:39:13 AM *To:* ausnog@lists.ausnog.net *Subject:* Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August Thanks guys, appreciate the feedback. At NEXTDC we wor

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August

2017-08-09 Thread Jared Hirst
EXTDC -Original Message- From: nat...@nightsys.net Sent: Thu, 10 Aug 2017 05:39:02 +1000 To: sh...@rackcentral.com Subject: Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August This seems reasonable? As long as no single Data Hall has both A and B feeds removed simult

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August

2017-08-09 Thread James Braunegg
.net] On Behalf Of Matthew Smee Sent: Thursday, 10 August 2017 12:00 PM To: ausnog@lists.ausnog.net Subject: Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August +1 Every DC agreement I’ve seen (3) have mentioned that you are responsible for supplying it with power and they aren’

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August

2017-08-09 Thread Matthew Smee
: Shaun McGuane Cc: ausnog@lists.ausnog.net Subject: Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August If you have single fed equipment in your rack that needs planning before it can be shut down, do you not run a totally forseeable and preventable risk then should that one

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August

2017-08-09 Thread Sam Silvester
oo. > > > > Happy to have a conversation offline about this feel free to give me a > call on my mobile. > > > > Regards > > Shaun > > > > > > > > *From:* AusNOG [mailto:ausnog-boun...@lists.ausnog.net > ] *On > Behalf Of *Simon Cooper > *Sent:* Thursd

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August

2017-08-09 Thread Shaun McGuane
Simon Cooper Sent: Thursday, 10 August 2017 8:39 AM To: ausnog@lists.ausnog.net Subject: Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August Thanks guys, appreciate the feedback. At NEXTDC we work very hard to keep critical infrastructure maintenance that impacts racks or the

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August

2017-08-09 Thread Karl Hardisty
centre operating safely and reliably for many years to come. > > Thanks, > Simon > COO, NEXTDC > > -Original Message----- > From: nat...@nightsys.net > Sent: Thu, 10 Aug 2017 05:39:02 +1000 > To: sh...@rackcentral.com > Subject: Re: [AusNOG] NextDC Melbourne - Scheduled Po

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August

2017-08-09 Thread Simon Cooper
Of Murat Sener Sent: Wednesday, 9 August 2017 3:20 PM To: Matthew VK3EVL <hit...@itglowz.com>; ausnog@lists.ausnog.net Subject: Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August   We have been told only Feed B in Data hall 2 will be effected as per original schedul

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August

2017-08-09 Thread Nathan Sullivan
gt; > > > Regards > > Shaun > > > > > > *From:* AusNOG [mailto:ausnog-boun...@lists.ausnog.net] *On Behalf Of *Murat > Sener > *Sent:* Wednesday, 9 August 2017 3:20 PM > *To:* Matthew VK3EVL ; ausnog@lists.ausnog.net > > *Subject:* Re: [AusNOG] Nex

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August

2017-08-08 Thread Shaun McGuane
From: AusNOG [mailto:ausnog-boun...@lists.ausnog.net] On Behalf Of Matthew VK3EVL Sent: Wednesday, 9 August 2017 3:13 PM To: ausnog@lists.ausnog.net<mailto:ausnog@lists.ausnog.net> Subject: Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August What about both feeds ha

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August

2017-08-08 Thread Murat Sener
g.net] On Behalf Of Matthew VK3EVL Sent: Wednesday, 9 August 2017 3:13 PM To: ausnog@lists.ausnog.net Subject: Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August What about both feeds happening on the same day at the same time? On 9/08/2017 2:55 PM, Shaun McGuane wrote: HI D

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August

2017-08-08 Thread Matthew VK3EVL
of them is switched off for these works? Regards Shaun *From:*Damien Gardner Jnr [mailto:rend...@rendrag.net] *Sent:* Wednesday, 9 August 2017 2:39 PM *To:* ; Shaun McGuane *Subject:* Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August It says 7am -> 4pm in what

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August

2017-08-08 Thread Shaun McGuane
] Sent: Wednesday, 9 August 2017 2:39 PM To: ; Shaun McGuane Subject: Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August It says 7am -> 4pm in what you quoted? (UTC+10 is AEST) On Wed, 9 Aug 2017 at 2:36 pm, Shaun McGuane mailto:sh...@rackcentral.com>> wrote: H

Re: [AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August

2017-08-08 Thread Damien Gardner Jnr
It says 7am -> 4pm in what you quoted? (UTC+10 is AEST) On Wed, 9 Aug 2017 at 2:36 pm, Shaun McGuane wrote: > HI Noggers, > > > > Has anyone seen this scheduled maintenance notification happening next > week? > > They maybe upgrading feeds or boards throughout the datacentre – has > everyone see

[AusNOG] NextDC Melbourne - Scheduled Power Maintenance - 15th August

2017-08-08 Thread Shaun McGuane
HI Noggers, Has anyone seen this scheduled maintenance notification happening next week? They maybe upgrading feeds or boards throughout the datacentre - has everyone seen this notification of works? It appears to be happening starting 5PM through to 2AM AEST for all Datahalls on the same date.