hi,
the same problem occurs for the production as well. did you receive
any solution offers about this?
whenever I have an order which exceeds the capasity of one shift it
doesn't consider transferin the work to the second shift but it
waits for the same work center comes on the next day...
Hi,
Could you please explain your answer to this question a bit more
detailed for me?
I'm having the same problem with the production scheduling and
couldn't figure out how to solve it with the solution you mention.
If we have a work center group (WCG) with 2 workers in it, working
in