This "issue" has been fixed by hotfix HF30SP3_002. After applying
the postings is corrected.
Regards
Eddie
--- In Axapta-Knowledge-Village@yahoogroups.com, jesse
<[EMAIL PROTECTED]> wrote:
> Dear Eddie,
>
> Thanks for your reply. What happens if i want to capitalise my
cost for my project
Dear Eddie,
Thanks for your reply. What happens if i want to capitalise my cost for my project? That is the reason why i selected Balance under Journalising in Project Group. If i select Profit and Loss under journalising the system post the correct transactions but not in the case when i se
--- In Axapta-Knowledge-Village@yahoogroups.com, jesse
<[EMAIL PROTECTED]> wrote:
> Dear all,
> Have anyone tested on Axapta Project module with Internal Project
type? The reason why I am asking this is because according to Axapta
Advance Project Guide for Internal Cost Project with WIP, syste