Hi Hardi,
I agree with Handan, Check the Load. Not in the work center group but check in the Production route. As i think It could be still show Load=0. Try to change the load in the production route with Load = 100% or other than 0%. And it will appear in your route card journal.
Regards
Hi Hardi, You must define a process (run) time for te Primary operation of the secondary operation.. if the you live it blank, the automatic routing journal will not create a line for the secondary oparetion even if you defined a setup time (or queue times) for primary operation I t
Hi Handan,
You mean "Load" under "Workcenter" field group on the general tab is
it?
My data shows 100, I suppose it means 100% is it? But still it is not
appear in my route card journal when I do start.
Thanks & regards
Hardi T
--- In Axapta-Knowledge-Village@yahoogroups.com, "HANDAN"
<[EM
Hi Tom,
Thanks for your reply.
You mean 4 check boxes for "process" line on the setup tab is it?
And the setup for "calculate process time" under "general" tab also
checked?
I've tried to set all these things but still my secondary operations
are not appear in the route card journal, what are th
Hi Hardi,
Please check your routing-group for the secondary priority. Be shure to
activate the checkmarks for process-time on TabPage "Setup".
Tom
--- In Axapta-Knowledge-Village@yahoogroups.com, "Hardi" <[EMAIL PROTECTED]>
wrote:
>
> Dear all
> When I start a production order, what is the reaso