[Axapta-Knowledge-Village] Re: Subcontracting production

2009-05-11 Thread edwardjosling
Thanks! Currently we are using one coverage group for the production (BOM) item as well as components. I've created now a separate group for the components and added the 30 days re-order margin for the bom item coverage group. Quickly tested and it seems to work. Thanks for the help!! Eddi

[Axapta-Knowledge-Village] Re: Subcontracting production

2009-05-11 Thread dynamics_man
Eddie Do not change the standard production leadtime to 60 days, since your production lead time is 30 days only. Add 30 days, ( your intimation advance timeline to your sub-contractor )in the coverage group, re-order margin for the production part. Try now, it will work. Dynamics_man --- I

[Axapta-Knowledge-Village] Re: Subcontracting production

2009-05-06 Thread mep53565
I think you can add Queue Time After to the production route. See Production/ Setup/ Route Groups. --- In Axapta-Knowledge-Village@yahoogroups.com, "edwardjosling" wrote: > > Hi All > > I have a query and hope that someone can help. > > We are using BOM's for final products with one level of