Hi,
What is the costing method used ?
HK
- Original Message
From: dj_rineer [EMAIL PROTECTED]
To: Axapta-Knowledge-Village@yahoogroups.com
Sent: Tuesday, March 25, 2008 8:46:27 AM
Subject: [Axapta-Knowledge-Village] ended production orders
I am on AX 3.0. Someone accidentally ended
-Village@yahoogroups.com
Sent: Tuesday, March 25, 2008 8:46:27 AM
Subject: [Axapta-Knowledge-Village] ended production orders
I am on AX 3.0. Someone accidentally ended a production order that had
too much production on it. I know you can not go back at this point and
correct the original production
Hi, The only way to do it is to make a rework order, in AX there is nothing
called a rework order, but the only workaround will be to make a prod order
of the quantity posted excess, remove the old BOM at production order level
and in the BOM line only put the required quantity of the finished
I am on AX 3.0. Someone accidentally ended a production order that had
too much production on it. I know you can not go back at this point and
correct the original production order but is there a way to back out
this excess production?