RE: [Axapta-Knowledge-Village] Multiple workcenters parallel using same
operation name
You
are correct about my setup erroring too. My memory did not me serve well. The
Step number needs to be the same but the Operation Name must be different.
Would be like this
ime with 2 different machines.
your setup shows an error too .
GOKHAN CAN
Kimden: Dick Howard [mailto:[EMAIL PROTECTED]
Gönderilmiş: Per 04.11.2004 16:28
Kime: [EMAIL PROTECTED]
Konu: RE: [Axapta-Knowledge-Village] Multiple workcenters parallel using
same oper
_
Kimden: Dick Howard [mailto:[EMAIL PROTECTED]
Gönderilmiş: Per 04.11.2004 16:28
Kime: [EMAIL PROTECTED]
Konu: RE: [Axapta-Knowledge-Village] Multiple workcenters parallel using
same operation name
The setup you show is erroring because the primary/secondary need to
reference the same
The setup you show is erroring because the primary/secondary need to
reference the same step and operation, not 10/20 and 1/2 like you have
attempted to define.
This Axapta function is commonly used to schedule secondary resources
for the same capacity reservation as the primary and would be used