Subject: [sudan-john-ashworth] Lamu abuzz with construction as South Sudan 
seeks new pipeline

1. Lamu abuzz with construction as South Sudan seeks new pipeline

The South Sudanese have said they want a pipeline up and running
within 18 months.” Umeme senior spokesperson Charlotte Kemigyisha

By JAINDI KISERO
The EastAfrican
Posted  Saturday, February 11  2012 at  15:53

A high level delegation from South Sudan has been in Kenya through the
week to initiate negotiations with over rights of passage for the
2,000 kilometre crude oil pipeline the country has decided to build to
connect its oil fields to the Kenyan coastal town of Lamu.

Initially, Juba said it would be building the pipeline on its own at
an estimated cost of $3 billion, with Kenya’s role limited to granting
right of passage. But it appears that as the negotiations progressed
last week, Juba realised that the scope of co-operation with Kenya on
the project will have to be much broader to leverage the latter’s
experience in executing large pipeline projects.

The climax of these preparations will be a groundbreaking ceremony to
be conducted by President Mwai Kibaki on March 2 that will mark the
start of the construction of the Lamu port. Ethiopian head of state
Meles Zenawi and President of South Sudan Salva Kiir are among the
dignitaries expected to attend the ceremony.

Last week, the joint implementation committee leading the negotiations
expanded the terms of engagement. The parties will be negotiating
terms and the role that Kenya can play in project execution support
and management of the pipeline when it is fully operational. The joint
committee is also negotiating issues such as immigration, transit
fees, and provision of security for the pipeline

Last week, the negotiating party agreed to appoint a transaction
adviser to advise on what are turning out to be complex negotiations.

With the government in Juba having decided that it will no longer
export crude oil through North Sudan, the need for an alternative
route to the sea is now more urgent than it has ever been for South
Sudan.

The South Sudanese have said they want a pipeline up and running
within 18 months.

Whether this is possible is debateable. But it is noteworthy that
China Engineering Pipeline Corporation (CPPEC), the Chinese contractor
working with the state-owned Kenya Pipeline Company, only recently
completed building a 400-kilometre pipeline between Nairobi and
Eldoret in a record 18 months.

Insiders have told The EastAfrican that due to the urgency with which
Juba wants a pipeline, the plan is to have multiple contractors
building different sections of the 2,000-kilometre pipeline.

For Kenya, the souring of relations between Juba and Khartoum offers
not only a great opportunity to boost its geostrategic significance as
the hub of economic activity in the region, but also an opportunity to
achieve its dream of acquiring a second transport and economic
corridor. Deepening economic relations with South Sudan and Ethiopia
will counterweigh the heavy dependence that Kenya currently has on
Uganda and Tanzania in the region.

Right now, Kenya only has one transport and economic corridor, the
Northern Corridor, starting from the port of Mombasa to Malaba on the
border with Uganda and onwards to Central Africa. A second corridor is
critical for Nairobi as Kenya wants to access Ethiopia and South Sudan
through northern and eastern parts of the country from the new port of
Lamu.

Kenya’s ultimate aim is to extend the transport corridor to Kigali all
the way to Douala in Cameroon. This will spawn a deeply
inter-connected economic zone straddling the Nile Basin countries that
will not only overshadow the ambitions of the East African Community,
but whose future will be shaped by regional trade in oil, gas and
electricity and the need to access the Indian Ocean.

Indeed, the battle over pipelines and access to the sea between
Khartoum and Juba has broken out just when Kenya is in the middle of
implementing its second corridor project.

A major project estimated to cost $15 billion, it has multiple parts
including the Lamu port itself, and a railway line and fibre optic
cable running from Lamu to South Sudan and Ethiopia through Isiolo.

The scope of the second corridor project includes airports at Isiolo,
Lamu and Turkana, a highway, an oil refinery at Lamu and resort
cities. But until the South Sudanese came up the other day, the only
project that was actually being implemented was the Lamu port.

Indeed, the scope of the second corridor project had been reduced to
the building of three berths to handle bulk cargo, general cargo and a
container terminal. The pressure by the South Sudanese was bound to
alter the equation, speeding up the construction pace of the port.

Repairs to road connections to places like Malindi, Witu and Garsen
are going on at a scale and pace never witnessed before. But the most
dramatic is the work currently going on the port area itself.

The whole port area is a massive construction site, with contractors
clearing bush and building road connections to the port area. The
construction of water and sanitation services and installation of
electric equipment has already started.

The contractors building the port office headquarters, a port police
station, and car parks moved to the site late week.

Controversies

Implementation of the Lamu project has not been without controversy. A
disagreement between the Ministry of Finance and the Treasury over the
cost of the feasibility study almost scuttled the whole project.
Well-connected individuals connived with land officials to allocate
themselves land on the port area, with the intention of selling it to
the government later at a huge profit. It has emerged that some of the
landowners had even charged the property to commercial banks for huge
advances.

The matter was only settled two months ago when the Cabinet resolved
that all titles in the proposed site of the port be cancelled by
decree and the land compulsorily acquired. What is clear is that the
entry of the South Sudanese into the fray has now altered the stakes.
Even with delays, the proposed Lamu port is set to be the region’s
largest oil exporting port.

http://www.theeastafrican.co.ke/news/South+Sudan+comes+to+town+shopping+for+Lamu+pipeline/-/2558/1324704/-/bltb84z/-/

END1

2. South Sudan in talks with Texas Company on oil pipeline

February 8, 2012 (DALLAS) – The government of South Sudan is in talks
with a Texas-based company to explore options for building an oil
pipeline which would serve as an alternative to the one passing
through the territories of Sudan.

According to South Sudan information minister Barnaba Marial Benjamin,
the unidentified company could start working the project in as soon as
six months.

He offered no further details.

The official further said that South Sudan had signed a memorandum of
understanding with Ethiopia to construct an oil pipeline passing
through Djibouti.

A source close to the Juba government said that Ethiopia’s Prime
Minister Meles Zenawi gave his approval to the idea. It is not clear
if Djibouti did the same yet. Eritrea is also an option on the table
even though its president Isaias Afewerki has yet to respond.

Last week, the former Sudan oil minister Lual Deng said that exporting
the oil through Djibouti would be a shorter distance than using the
established pipeline going all the way from South Sudan to the Red
Sea.

South Sudan minister said that Toyota Company has started feasibility
studies on the Lamu pipeline project which was signed recently with
Kenya.

The landlocked nation is currently involved in an escalating dispute
with Khartoum over the payment of transit fees for its oil.

Negotiations between Juba and Khartoum, hosted by the African Union
High-level Implementation Panel (AUHIP) have thus far failed to find a
resolution.

Khartoum demands South Sudan pays $32 per barrel of oil that passes
through its territory. Juba says it will only pay around $1 a barrel.

As talks on the fees dragged on the Sudanese government said it ran
out of patience and can no longer tolerate South Sudan exporting its
oil for free. As such it started taking part of the oil pumped by
South Sudan to make up for what it called unpaid fees.

In response, South Sudan said last month it was shutting down its output.

(ST) http://www.sudantribune.com/South-Sudan-in-talks-with-Texas,41552

END2
______________________
John Ashworth

Sudan, South Sudan Advisor

[email protected]

+254 725 926 297 (Kenya mobile)
+211 919 695 362 (South Sudan mobile)
+27 82 050 1235 (South Africa mobile)
+44 750 304 1790 (UK/international)
+88 216 4334 0735 (Thuraya satphone)

PO Box 52002 - 00200, Nairobi, Kenya

This is a personal e-mail address and the contents do not necessarily
reflect the views of any organisation

-- 
The content of this message does not necessarily reflect John Ashworth's views. 
Unless explicitly stated otherwise, John Ashworth is not the author of the 
content and the source is always cited.

You received this message because you are subscribed to the Google Groups 
"sudan-john-ashworth" group.
To post to this group, send email to [email protected]
To unsubscribe from this group, send email to 
[email protected]
For more options, visit this group at 
http://groups.google.co.za/group/sudan-john-ashworth

-- 
You received this message because you are subscribed to the Google Groups 
"South Sudan Info - The Kob" group.
To post to this group, send email to [email protected].
To unsubscribe from this group, send email to 
[email protected].
For more options, visit this group at 
http://groups.google.com/group/SouthSudanKob?hl=en.

Reply via email to