On Mon, Nov 24, 2008 at 10:07 PM, Partha Aji <[EMAIL PROTECTED]> wrote:
> Mike McCune wrote:
>>
>> Jesus M. Rodriguez wrote:
>>>
>>> Hey Spacewalk hackers,
>>>
>>> I'd like to wrap up feature and bug fixing by 12/5 so that we can
>>> start the package building process on Monday 12/8 for a release on
>>> 12/15. Let me know if this will be a problem.
>>>
>>> Feature freeze: 12/5
>>> Packages: 12/9
>>> QA freeze: 12/12
>>> Release: 12/15
>>>
>>
>> I'm thinking since the scope of features in 0.4 is much much larger than
>> the previous releases we are going to need to spend more time in testing
>> (multiorg and cobbler-koan come to mind)
>>
>> I'd advocate we instead release a QA build to the public on 12/15 and do
>> the final release on say ... 12/22?  Or after the break?  I realize I'm
>> calling for us to be late but it seems rational to me.
>>
>> Anyone else agree/disagree?
>>
> +1. The cobbler koan feature will require significant testing w.r.t
> provisioning especially. 12/15 release at this point seems a bit too
> optimistic IMHO.
>
> _______________________________________________
> Spacewalk-devel mailing list
> Spacewalk-devel@redhat.com
> https://www.redhat.com/mailman/listinfo/spacewalk-devel
>
>From a community perspective, having 0.4 after the holidays probably
isn't a problem.  Most people are minimally staffed and don't have a
ton of time to try out new things.  Also, things working is better
than meeting a date.

stahnma