Got a project where
the decision to sprinkler a 600 ft²
storage facility (possibly plastics to
10 ft) mixed with an additional 600 ft²
office area was nixed, because
the Codes didn´t require it (not
enough area to justify it).

I can do the risk analysis, and accept
letting the building burn to the ground,
because no one else is around for
60 ft.  But to hear the GC say he
did the client a favor by saving
them maintenance costs in nixing
the sprinkler system is akin to
leaving the second parachute out
to save packing time.

but yes i agree
that clients
of some occupancies
should still have the
option of not to install them.

scot deal
excelsior fire engineering
_______________________________________________
Sprinklerforum mailing list
[email protected]
http://lists.firesprinkler.org/mailman/listinfo/sprinklerforum

To Unsubscribe, send an email to:[EMAIL PROTECTED]
(Put the word unsubscribe in the subject field)

Reply via email to