yes i would want the contractor to install new UG.and i would expect them to get a change-order if the contracts/specs warranted it.
i don´t know how far to go in demanding documentation of the UG. UG and waterflow infor are important, that much I know. because there were 'significant sprinklers and armovers´ being changed i thought the mains should be braced, but am MORE than willing to embrace the idea that I am asking for more than the standard-of-care. Thank you for educating me in this subject. scot deal excelsior fire On Fri, May 8, 2009 at 9:23 PM, Forest Wilson <[email protected]>wrote: > Depends on the contractors bid and contract, not NFPA. > I exclude pre-existing conditions like the bracing of existing main piping? > Sounds like you want the existing system brought up to current standards > and codes when all they need to do is move 200 armovers. > Contract and specs rule this. What if calculations indicate inadequate > water supply? Are you then wanting the contractor to install new UG? _______________________________________________ Sprinklerforum mailing list http://lists.firesprinkler.org/mailman/listinfo/sprinklerforum For Technical Assistance, send an email to: [email protected] To Unsubscribe, send an email to:[email protected] (Put the word unsubscribe in the subject field)