Thank you all for your help. That is what I thought but we were starting to 
wonder if we were the only ones that seem to consistently have this problem. We 
so clearly, in bold exclude it in detail and then still end up with a fight at 
the end because the GC didn't buy it out. We were considering just including 
all of it in all of our preaction bids so they get a complete system and 
eliminate the hassle but felt that this would make us less competitive if 
others weren't doing the same. We will continue to exclude and see if we can't 
find a better way to communicate that this is a likely scope gap unless it is 
addressed at bid time.

-----Original Message-----
From: Sprinklerforum [mailto:[email protected]] On 
Behalf Of rongreenman .
Sent: Tuesday, February 09, 2016 11:03 AM
To: [email protected]
Subject: Re: Preaction Systems Scope

Here it is typically handled like Mike describes too. Everyone pretty much 
knows the general's contracts guy will miss all the exclusion clauses unless 
he's been bitten before. The object is to get the building built with all 
systems working.

On Tue, Feb 9, 2016 at 9:53 AM, Morey, Mike <[email protected]> wrote:

> Typically we tried to let the project team work it out, but if they 
> didn't or there wasn't a well defined project team to resolve these 
> issues we'd typically take it out for numbers.  Usually we try and get 
> the electrical/alarm bidders for the project to put a number on it.
>
> Mike Morey, CFPS, SET
> Planner Scheduler/Designer
> BMWC Constructors, Inc.
> 1740 W. Michigan St, Indianapolis, IN 46222
> O: 317.651.0596 | C: 317.586.8111
> [email protected] | www.bmwc.com
>
> ________________________________________
> From: Sprinklerforum <[email protected]> 
> on behalf of Rod DiBona <[email protected]>
> Sent: Tuesday, February 9, 2016 12:25 PM
> To: [email protected]
> Subject: Preaction Systems Scope
>
> I am wondering how most of you handle the detection and releasing 
> systems for your preaction systems. We traditionally have excluded all 
> electrical and alarm but find it very common that the fire alarm 
> contractor was just smarts and parts and the electrician doesn't have 
> it in his scope. Not very often have the ME and EE coordinated so that it is 
> spelled out correctly.
> So my question is do most of you include this scope and have an 
> electrical subcontractor that runs the conduit, provides and installs 
> the heats or detectors and programs the releasing panel or do you 
> exclude? Thanks
>
>
> Rod at Rapid Fire
>
>
>
> _______________________________________________
> Sprinklerforum mailing list
> [email protected]
>
> http://lists.firesprinkler.org/listinfo.cgi/sprinklerforum-firesprinkl
> er.org _______________________________________________
> Sprinklerforum mailing list
> [email protected]
>
> http://lists.firesprinkler.org/listinfo.cgi/sprinklerforum-firesprinkl
> er.org
>



--
Ron Greenman
Instructor
Fire Protection Engineering Technology
Bates Technical College
1101 So. Yakima Ave.
Tacoma, WA 98405

[email protected]

http://www.bates.ctc.edu/fireprotection/

253.680.7346
253.576.9700 (cell)

Member:
ASEE, SFPE, ASCET, NFPA, AFSA, NFSA, AFAA, NIBS, WSAFM, WFC, WFSC

They are happy men whose natures sort with their vocations. -Francis Bacon, 
essayist, philosopher, and statesman (1561-1626)

A problem well stated is a problem half solved. -Charles F. Kettering, inventor 
and engineer (1876-1958) _______________________________________________
Sprinklerforum mailing list
[email protected]
http://lists.firesprinkler.org/listinfo.cgi/sprinklerforum-firesprinkler.org

_______________________________________________
Sprinklerforum mailing list
[email protected]
http://lists.firesprinkler.org/listinfo.cgi/sprinklerforum-firesprinkler.org

Reply via email to